What does the CDM Regulations 2015 stand for?
ANSWER ✔✔
The Construction (Design and Management) Regulations 2015
When did the CDM Regulations 2015 come into force?
ANSWER ✔✔
06 April 2015
Who are the duty holders under the CDM Regulations 2015?
ANSWER ✔✔
Commercial client
Domestic client
Principal designer
Designer
Principal contractor
Contractor
Worker
What are the main duties of the client?
ANSWER ✔✔
Make suitable arrangements to manage a project to ensure construction works are carried
out safely and adequate welfare facilities are provided.
Provide the pre-construction information.
Ensure the appointment of the principal designer and principal contractor in writing
before the construction phase begins.
Ensure both the principal designer and principal contractor comply with their own duties.