29. The construction contract requires the contractor to submit a
complete schedule. This draft so far includes work activities, their
duration, and milestones. Which of the following other information is
necessary to develop this schedule?
a. OSHA inspections
b. Procurement of long lead items
c. Schedule of values
d. List of payment application document. --- correct answer ---b.
Procurement of long lead items
30. In creating a schedule, which of the following occurs first?
a. Develop the logic
b. Perform the duration calculations
c. Identify the activities
,b.Input the information into the network --- correct answer ---c.
Identify the activities
31. Who is responsible for inspecting for safety risks on a project prior
to operation?
a. Project superintend
b. Company safety officer
c. Structural steel Forman
d. Designated competent person. --- correct answer ---d. Designated
competent person.
32. What format is based on the CSI conceptual estimating systems?
a. Uniformat
b. Section format
c. Master format
d. Project Manuel format --- correct answer ---c. Master format
,33. What is the best action for a contractor to take concerning a
project that is one month behind schedule due to incomplete and late
architectural drawings?
a. Work overtime to meet the completion date and not bid for the
premium time.
b. Updated the schedule and notify the owner of the options and
associated costs
c. Inform all subs that the schedule must be made and extra
compensation will be paid
d. Create a revised construction schedule with the assistance of the
architect --- correct answer ---b. Updated the schedule and notify the
owner of the options and associated costs
34. When the start of one activity depends on the completion of the
preceding activity, the relationship on a logic network of the two
activities is a
a. Finish to Finish
b. Finish to Start
c. Start to Finish
d. Start to Start --- correct answer ---b. Finish to Start
, 35. To conduct an effective team meeting, it is best to
a. Develop an agenda for own use only
b. Develop a list of topics for the agenda at the begging of the meeting
so that everyone has input.
c. Hand out an agenda and see the team member has it prior to the
meeting so they can come prepared.
d. Develop an agenda and see that team members have it prior to the
meeting so they can come prepared --- correct answer ---c. Hand out
an agenda and see the team member has it prior to the meeting so
they can come prepared.
36. A light fixture slides of the electrical subcontractors scaffolding in
the lobby of a new bank building. The result is several hundred dollars
in damage to the floor finish. Workers below could have been hit by
the falling fixture. Which of the following is the best course of action
to take?
a. Proceed with electrical installation after the subcontractor has
cleaned the area
b. Ensure presence of OSHA approved railing, toe boarding and netting
on all scaffolds