What are the three Innovation & Design Process TOPICS? - ✔✔1. Integrated Project
Planning
2. Durability Management Process
3. Innovative or Regional Design
Integrated Project Team members are considered to have what types of SKILL SETS? -
✔✔- Architecture or Residential Building Design
- Mechanical or Energy Engineering Building Science or Performance testing
- Green Building or sustainable design
- Civil engineering Landscape architecture
- Habitat restoration Land use planning
WHEN should a design Charrette take place? - ✔✔No later than the Design
Development phase
&
COPYRIGHT © 2025 BY GRACE AMELIA, ALL RIGHTS RESERVED 1
,preferably during Schematic Design
HOW LONG should a design Charrette last? - ✔✔At least (1) Full Day
What are the three BUILDING ORIENTATION requirements for Solar Design ? - ✔✔1.
South-facing glazing area is at least 50% greater than the sum of the glazing area on East
& West walls.
2. East-West axis of building is within 15° of due East-West.
3. 90% of South-face glazing wall is shaded at 12PM on June 21 and unshaded at 12PM
on December 21.
What are the LEED for Homes CERTIFICATION levels and associated point ranges? -
✔✔Certified 40-49
Silver 50-59
Gold 60-79
Platinum 80-110
What is meant by a Durability Management Verification? - ✔✔A 3rd Party Green Rater
has inspected & verified each measure listed in the Durability Inspection Checklist
- ENERGYSTAR Water Management Systems
The Material and Resources Prerequisite for Durability Management addresses which
condition? - ✔✔Indoor Moisture Control Measures
What are the four project specifications that must be addressed when designing
durability? - ✔✔1. Water Managed Site and Foundation
COPYRIGHT © 2025 BY GRACE AMELIA, ALL RIGHTS RESERVED 2
, 2. Water Managed Wall Assembly
3. Water Managed Roof Assembly
4. Water Managed Building Materials
Projects that do not participate in LEED for Neighborhood Development may pursue
what STRATEGIES? - ✔✔Site Selection
- Sensitive land protections
- Infill development
- Open Space
- Street Network
- Bicycle Network and Storage
Compact Development
Community Resources
Access to Transit
Under LT: Site Selection, what is considered an ENVIRONMENTALLY SENSITIVE
site? - ✔✔Prime Farmland