HOW TO PASS 3 Hours OPMA 3306 OPERATIONS MANAGEMENT Final Exam Review University of Texas, Arlington
HOW TO PASS 3 Hours OPMA 3306 OPERATIONS MANAGEMENT Final Exam Review University of Texas, Arlington Problem 5-7 There is an 83% chance the project below can be completed in D weeks or less. ACTIVITY MOST OPTIMISTIC MOST LIKELY MOST PESSIMISTIC A 5 5 11 B 2 2 2 C 4 2 9 D 8 9 13 E 7 10 10 What is D? (Round your answer to the nearest whole number.) 5-7 ANSWER: First find the value of Z that results in a probability of 0.83 on Table. Z = 0.9542 Then find the critical path (ACE) and the variance on the critical value is 1.944. - Use equation to solve for D: D−T E Z √∑ σ 2
Geschreven voor
- Instelling
- University Of Texas - Arlington
- Vak
- OPMA 3306
Documentinformatie
- Geüpload op
- 8 mei 2025
- Aantal pagina's
- 17
- Geschreven in
- 2024/2025
- Type
- Tentamen (uitwerkingen)
- Bevat
- Vragen en antwoorden
Onderwerpen
-
how to pass 3 hours opma 3306 final exam