Which of the following is the NERC Criteria for having to report a BES
emergency that resulted in manual load shedding?
100 MW
Which of the following is the NERC Criteria for having to report a BES
emergency that resulted in a voltage deviation on a facility?
A) 15% excursion for no longer than 15 minutes
B) 10% excursion for longer than 15 minutes
C) 10% excursion for no longer than 15 minutes
D) 15% excursion for longer than 15 minutes
B) 10% excursion for longer than 15 minutes
How soon does a Transmission Operator have to update its restoration
plan after identifying any unplanned permanent System modification?
A) 30 days
B) 45 days
C) 90 days
,D) 15 days
C) 90 days
Each Transmission Operator and Balancing Authority shall verify the
restoration procedure by
Testing
A _________experiencing a reportable incident as detailed by the NERC or
DOE reporting procedures shall provide a preliminary written report to its
Regional Reliability Organization and NERC/DOE.
A) Generator Operator
B) Load Serving Entity
C) Reliability Coordinator
D) All of the above
D) All of the above
Each Reliability Coordinator shall be aware of the restoration plan of each
Transmission Operator in its Reliability Coordinator Area in accordance
with ____________requirements.
NERC and Regional
Each Reliability Coordinator, Balancing Authority, and Transmission
Operator, shall review and approve its Operating Plan for backup
functionality on what interval?
Annually
, The plan for the Loss of Control Center Functionality shall include
procedures and responsibilities for compliance with
Reliability Standards
What is the time limit for the transition period between loss of primary
control center functionality and time to fully implement backup
functionality?
A) Three hours
B) Two hours
C) Five hours
D) One hours
B) Two hours
During an EEA 1, which of the following best describes what the deficient
entity is attempting to do?
Increase its generation supply.
Why should a Balancing Authority not unilaterally adjust generation in an
attempt to return Interconnection frequency to normal beyond that
supplied through frequency bias action and Interchange Schedule
changes?
Such unilateral adjustment may overload transmission facilities.
Each Transmission Operator and Balancing Authority shall develop,
maintain, and implement a set of plans to mitigate operating emergencies
for which of the following?