Exam Questions With Reviewed
100% Correct Detailed Answers
Guaranteed Pass!!
1. The three types of agencies responsible for administering and enforcing
Part 91 are _____, _______, and _______. - ANSWER CEA, MEA, APA
2. The ______ and _______ issue SESC permits whereas the _____ undertake
earth change activities in accordance with procedures submitted to the
MDEQ. - ANSWER CEA, MEA, APA
3. The Part 91 inspector must regularly ______ the project site to determine if
the SESC measures are properly ________ and _______ in accordance with
the SESC plan and if the SESC measures are _______ in minimizing erosion
and off-site sedimentation. - ANSWER Inspect, Installed, Maintained,
Effective
4. Part 91 inspectors are responsible for ensuring or verifying that:
a) SESC permits are ______ on site.
b) Inspections are done in a manner and ________ to assure minimization of
_______ and off-site __________.
c)Inspections are properly __________.
, d) SESC measures are properly installed and maintained per standard details or
plan _________ and are _________. In addition, the inspector must be
__________ and anticipate or assess potential problems that may occur.
e) Sediment caused by accelerated erosion does not ________ the project site.
f) Water discharged from the site is at _____-_________ velocities.
g) Temporary SESC measures are installed _______ or upon __________ of the
earth change activity.
h) Temporary SESC measures are maintained on a ______ basis.
i) Permanent SESC measures are installed on all slopes, channels, ditches, or any
disturbed land within _____ calendar days after final grading.
j) Projects - ANSWER a) Posted
b) Frequency, Erosion, Sedimentation
c) Documented
d) Specifications, Effective, Proactive
e) Leave
f) Non-Erosive
g) Before, Commencement
h) Daily
i) 5
j) Stabilized, Removed
k) Compliance, Enforcement
5. Any violation of Part 91, the Rules, applicable SESC ordinance approved
SESC procedures, approved SESC plans or SESC permit conditions subjects