1. What FAR part covers protests? - ANSWER FAR Part 33.
2. A postaward orientation aids both government and contractor personnel to:
- ANSWER Achieve a clear and mutual understanding of all contract
requirements and identify and resolve potential problems.
3. What agency does DoD typically delegate contract administrative
responsibilities for supply contracts? - ANSWER Defense Contract
Management Agency (DCMA).
4. Can a contractor file a protest at any time it chooses? - ANSWER No,
there are established timeframes within which a contractor must file its
protest.
5. What will the government do when late in paying an otherwise acceptable
invoice? - ANSWER Pay an interest penalty.
6. What is true about the acquisition team according to FAR 1.102-3? -
ANSWER Includes the contractor.
,7. Which payment form is required for an online subscription with upfront
payment? - ANSWER An advance payment.
8. When acquiring commercial items, quality assurance is primarily the
responsibility of: - ANSWER The contractor.
9. What is a purpose of a postaward orientation? - ANSWER Achieve a
clear and mutual understanding of all contract requirements.
10.Which statement is true about contractors and government property? -
ANSWER The contractor will have to pay for the test fixture.
11.In ensuring overall quality of items and services received under a contract,
which is the government's responsibility? - ANSWER Quality assurance
surveillance.
12.What is the government's preferred remedy to nonconforming goods or
services? - ANSWER Allow the contractor to repair or replace the
nonconforming items, as long as there is still time left within the required
delivery schedule.
13.Quality assurance policies and procedures found in FAR Part 46: - ANSWER
Apply to both the government and contractor.
14.When is a CPARS report required? - ANSWER When the contract dollar
value exceeds the simplified acquisition threshold.
,15.What are contractors responsible for? - ANSWER Tendering to the
government for acceptance only those supplies or services that conform to
contract quality requirements.
16.Does the government have the right to inspect a product before
acceptance? - ANSWER Yes, always.
17.Quality assurance on contract actions below the SAT is: - ANSWER
Minimal, unless a special circumstance exists.
18.In commercial contracting, what quality system is utilized? - ANSWER
The contractor's.
19.According to the FAR, acceptance of supplies or services is the responsibility
of: - ANSWER The contracting officer.
20.Which statement about Small Business Subcontracting Plans is accurate? -
ANSWER Required for contracts with large businesses, regardless of
location.
21.Who develops quality requirements essential to ensuring contract integrity?
- ANSWER The activity responsible for technical requirements.
22.When does the title of a completed product transfer to the government? -
ANSWER Upon formal acceptance by the government.
, 23.Does the government's policy to require contractors to incorporate
commercial items apply to subcontractors at all levels? - ANSWER Yes.
24.Which modification must be issued bilaterally? - ANSWER Making a
negotiated equitable adjustment caused by a change order.
25.Change orders issued under the changes clause of the contract use which
form? - ANSWER SF 30.
26.Which entity has privity with a first-tier subcontractor? - ANSWER The
prime contractor.
27.What are the two types of contract modifications? - ANSWER Unilateral
and bilateral.
28.Which FAR part is titled "Subcontracting Policies and Procedures"? -
ANSWER FAR Part 44.
29.Which contract modification must be signed by both the contractor and the
contracting officer? - ANSWER An agreement definitizing a letter
contract.
30.Where can contractors appeal a contracting officer's final decision? -
ANSWER The U.S. Court of Federal Claims.