A cumulative list of job deficiencies/rework items can be found in: correct answers Quality
Control Report
Contractor benefits of CQM correct answers Increased profit and production, better
communications, planning, improved organizational skills, and outstanding performance
evaluations to obtain future contracts.
contractor quality control function correct answers To assure that the completed project meets all
quality requirements of the contract.
Purpose of CQM correct answers The government's efforts, separate from, but in coordination
and cooperation with the contractor, assure that the quality set by the plans and specifications is
achieved.
Two factors cause construction industry to become highly specialized correct answers changing
markets and increased tech and regulations
Factor that will influence both government and construction industry in the future correct
answers New government regulations, greater influence from consumer, improvement in QC and
QA requirements, construction-oriented management info systems, formal partnering involving
stakeholders, more reliance on design-build, more considerate for live cycle requirements and
increased based incentives
A definable feature of work: correct answers Can consist of a combination of multiple
specification sections depending upon the nature of the work
Actual construction on the jobsite begins: correct answers After an interim or final QC is
accepted
, All submittals for government approval must be provided by the _________________ in time to
allow for the review, approval, procurement, delivery, and performance of preparatory phase for
an item before it is needed for construction. correct answers Contractor to the Government
An effective contractor quality control program will correct answers Be an incentive for work to
be done correctly the first time resulting in earlier completion, reduced field overhead costs, and
greater profits
Characteristics that describe a definable feature of work include: correct answers Cross-
referenced listings to the contractor's construction schedule that may have more than one
definable feature under a section of the specifications
Construction Quality Management is the performance of tasks, which ensure that construction is
performed: correct answers According to plans and specifications, on time, within a defined
budget and a safe work environment
Contractor testing procedures: correct answers are outlined in the Quality Control Plan as
defined by section 0145N/01451A and addressed at the Coordination and Mutal Understanding
Meeting (Navy).
Control is correct answers A continual system of planned future activities (its preventative)
Design-Build contracts require correct answers The QC Manager to be in place and take an
active role in the review and coordination of the design.
During the punch-out inspection of a project: correct answers The contractor prepares a punch
list and makes corrections
ENG Form 4288-R, the submittal register correct answers identifies this submittals requiring
government approval