In order to accurately estimate Spill start time, spill end time and spill rate
the flow of a sanitary sewer
overflow (SSO) you must have:
Providing a plan and schedule A sewer system management plan (SSMP)
to properly manage, operate
and maintain all parts of the
sanitary sewer system is the goal
of a:
What are the basics elements of Safety policy, statement, safety training, accident investigation
a safety program?
What factor must be considered Access for equipment and personnel
when obtaining an easement for
construction and maintenance
of a collection system?
As the division manager you Respond with the information available and update them with
receive a request from your more
board or council, and they want
an immediate response. You do
not know all the answers you
should:
If you were a supervisor of two Discuss the problem with the substandard foreman and offer to
lead workers, one whose work help before any other action is taken
was exceptionally good and a
second whose work was
substandard, what should you
do?
, In selecting pipe material for Life expectancy of pipe
maximum service life which
factor is more important?
What affects the flow capacity Pipe size, pipe, material, grade
of a sewer line?
When a grade conflict exists Have the Water main adjusted and hold the grade on the sewer
between a Water main and a main
sewer main, which of the
following is the best solution?
Why is the replacement of Crowding of other underground utilities.
wastewater collection systems in
some downtown streets
difficult?
Under what conditions must At least once a year in simulated situation using non-
each member of the rescue representative space conditions
service practice permit space
rescues?
If the camera becomes wedged Attempt to free the camera with the tag line.
during a video inspection, which
of the following would be your
first step in solving the
problem?
Drawings which are considered Corrected construction drawings showing changes made in the
"As Built" would be? field installation.
Legally Responsible Officials are Within 2 hrs.
required to report category 1
sanitary sewer overflows:
Span & Control relates to the 9 to 11
number of subordinates who
can be supervised effectively by
one supervisor. At the top level
of organizations, what is this
number?
What is the best approach to Communicate clearly without attacking the other person or
take when handling on-the-job personalizing the conflict
conflicts?
What tools are used with a Spring blades
power rodder?
Tools used for sewer rodding do Lag screw
not include the:
What items would you consider Cause of stoppage
when selecting a solution to
clear a stoppage in a sewer?
The lowest point on the inside of Invert
a pipeline is called the:
Emergency stoppages in High velocity cleaners (HVC)
pipelines may be cleared safely
by use of: