Project task E has the following estimates: (1) optimistic time = 10 days,
(2) Pessimistic time = 20 days, and (3) Most likely time = 12 Days. The
expected time using the beta statistical distribution is __________ days.
Your answer:
13 DAYS( Thirteen days)
pts
Question 2
Tim is planning the budget for his project with the team. He tells them that it's
likely that the majority of the money will be spent during which of the following
processes?
Perform Integrated Change Control
Monitor and Control Project Work
Correct!
Direct and Manage Project Execution
Verify Scope
https://northeastern.instructure.com/courses/139932/quizzes/497722/history?version=1 1/24
,12/11/23, 1:39 PM Elisha Nakka (She/Her)'s quiz history: PJM5900_Final Exam
Correct! Direct and Manage Project Execution is the process of
performing the work defined in the project management plan to
achieve the project’s objectives. Thus, this is the process in which
costs (e.g., material and labor costs) are incurred.
pts
Question 3
All of the following statements are true except for which one?
A project may or may not be part of a program
Project life cycles are collections of sequential and occasionally
overlapping project phases.
Correct! Portfolios are collections of interdependent projects or programs
Programs are groups of related projects
Correct! A project Portfolio is a collection of projects or programs and
other work that are grouped together to facilitate effective management of
that work to meet strategic business objectives. The projects or programs of
the portfolio may not necessarily be interdependent or directly related.
pts
Question 4
Open the attached file to answer this question. Remember to close the
file before moving to the next question. The attached network diagram
would be best described as:Q_49_ND.pdf
https://northeastern.instructure.com/courses/139932/quizzes/497722/history?version=1 2/24
, 12/11/23, 1:39 PM Elisha Nakka (She/Her)'s quiz history: PJM5900_Final Exam
(https://northeastern.instructure.com/assessment_questions/332142/files/540657/download?
verifier=82oe3oKikkvt0tyimPpgcsOcbuWf29ORbYax1ECV&wrap=1)
Correct! AOA diagram
AON diagram
PDM diagram
AAO diagram
Correct! This diagram shows an activity on arrow network in which
the activities are shown on the arrows and the (circular) nodes
represent events.
pts
Question 5
A major output and deliverable from the project start-up and planning
phase that contains the best estimate of a project’s scope, benefits, costs,
risks, and resource requirements defines the:
Information Systems Plan
Statement of Work
Correct! Baseline Project Plan