AND ANSWERS WITH RATIONALES|ALREDY
GRADED A+
Product-process matrix - ANSWER- a framework depicting when the different
production process types are typically used, depending on product volume and how
standardized the product is.
the horizontal access shows the volume of a particular product.
The vertical access shows standardization, variations in the product that is produced.
This is measured in terms of differences. Highly Standardized is highly similar. Low
standardized are different in their processes of production.
it is desirable to design processes along the diagonal.
Depending on where your product lands (medium product volume/product
standardization would land in the manufacturing cell) determines the environment you
should use. Some of the layouts span across large areas of this framework.
special-purpose equipment - ANSWER- more specialized, often available as an
alternative to a general-purpose machine.
Example: special-purpose drill, drill press
break-even analysis - ANSWER- Step 1: Find the demand by comparing two processes.
2500 + 25 U = 2600 + 26 U, solve for U to find demand.
Step 2: Find the one with less cost for demand of less then or greater then the demand.
The point where we are indifferent between two options. the process of evaluating
different production level trade-offs in order to break even. Must consider the cost of the
equipment, the setup time, and the time per unit. Choose among alternative processes
or equipment. Presents alternative profits and losses due to the number of units
produced or sold.
Depends on demand, most suited for large initial investments and fixed costs, when
variable costs are reasonably proportional to the number of units produced. can
approach at cost minimization or profit maximization.
break-even analysis example: Given the following options
, 1. Buy the part for 200 per unit
2. buy a machine and make the part for 75$ per unit, where the machine costs 80,000
3. buy a machine center and make the part for 15$ per unit, where the center costs
200,000
Given demand of over 2,000 units, what is the best option for lowest cost?
Given demand between 640-2,000 units, what is the best option for lowest cost?
Given demand under 640 units, what is the best option for lowest cost? - ANSWER-
With a demand of over 2,000 units, the costs are as followed:
1. 200 per unit * demand of 2,001= 400,200
2. 75 per unit * demand of 2,001 + 80,000= 230,075 3. 15 per unit *
demand of 2,001 + 200,000= 230,015 So buying the machine
center is the best option.
With a demand between 640-2,000 units, the costs are as followed:
1. 200 per unit * demand of 641= 128,200
2. 75 per unit * demand of 641 + 80,000= 128,075 3. 15 per unit *
demand of 641 + 200,000= 209,615 So buying just one machine is
the best option.
With a demand under 640 units, the costs are as followed:
1. 200 per unit * demand of 639= 127, 800
2. 75 per unit * demand of 639 + 80,000= 127,925
3. 15 per unit * demand of 639 + 200,000= 209,585
So buying the product from someone else is the best option.
Manufacturing process flow design - ANSWER- evaluates the specific processes that
raw materials, parts and sub assemblies follow as they move through the plant. Design
is made up of: assembly drawing, assembly chart, operation and route sheet, and flow
process charts. Focus should be on identifying activities that can be minimized or
eliminated. Fewer the moves, delays and storage, the better the flow.
Breakeven analysis example: 3 different processes
Process: 1, fixed cost of 18,500 VC 35
Process: 2, fixed cost of 20,000 VC 25
Process: 3, fixed costs 23,000 VC 20
Which production process should we select?
Getting breakeven point between 1 & 2? If the demand is above 150, which process
should we select?