Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

NERC Exam Questions – A+ Graded Submission – 100% Verified Q&A for Success – Passed with Distinction

Beoordeling
-
Verkocht
-
Pagina's
32
Cijfer
A+
Geüpload op
29-05-2025
Geschreven in
2024/2025

NERC Exam Questions – A+ Graded Submission – 100% Verified Q&A for Success – Passed with Distinction

Instelling
NERC
Vak
NERC

Voorbeeld van de inhoud

NERC Exam Questions – A+ Graded Submission
– 100% Verified Q&A for Success – Passed with
Distinction Updated for 2025
System operator training program criteria should be based upon all of the following EXCEPT:

A. FERC criteria

B. Regional council policies

C. NERC operating policies

D. Regulatory requirements - ✔✔A. FERC criteria



Which of the following actions is used to prevent a voltage collapse when reactive resources are
insufficient?

A. Lower transmission voltage regulator settings

B. Implement load reduction

C. Offset scheduled frequency

D. Reduce generator output - ✔✔B. Implement load reduction



NERC policies define the term "interchange" as:

A. Demand that can be interrupted by direct action of the supplying system's system operator

B. The amount of electric power delivered or required at specific points on the system

C. Energy transfers across control area boundaries

D. A plan or arrangement for transaction - ✔✔C. Energy transfers across control area boundaries



Emergency actions for immediately responding to a sudden generation capacity deficiency may include:

A. Purchasing economic energy

B. Starting another fossil fuel unit

C. Scheduling available emergency assistance and implementing load shedding

D. Postponing equipment maintenance on units if it will derate the unit by 10% or more - ✔✔C.
Scheduling available emergency assistance and implementing load shedding

,During low load conditions, what are the primary system conditions the system operator works to
alleviate?

A. High voltage and overgeneration

B. Low voltage and overgeneration

C. High voltage and undergeneration

D. Low voltage and undergeneration - ✔✔A. High voltage and overgeneration



Who is responsible for developing procedures to provide transmission security?

A. NERC

B. FERC

C. The subregion

D. The control area - ✔✔D. The control area



Planned transmission outages shall be coordinated with:

A. Power marketers

B. Generation suppliers

C. NERC regional council

D. Any system (or entity) that may be affected - ✔✔C. NERC regional council



How often does NERC recommend that studies be made to determine the transfer capability between
interconnected control areas?

A.. Monthly

B. Quarterly

C. Annually

D. Biannually - ✔✔C. Annually



What is the data retention requirement for any control area or region to retain data made available on
the Interregional Security Network (ISN)?

A. 1 month

,B. 6 months

C. 12 months

D. 0 months - ✔✔D. 0 months



As a general rule (preference not requirement), digital data should be sampled every :

A. 2 seconds

B. 4 seconds

C. 6 seconds

D. 8 seconds - ✔✔B. 4 seconds



Results of the NERC hotline test shall be reported to the NERC operations committee each:

A. Day

B. Month

C. Quarter

D. Year - ✔✔C. Quarter



Under normal conditions, what is the primary reason AGC equipment should remain in-service?

A. To regulate control area interties

B. To regulate non-spinning reserve

C. To adjust for poor load forecasting

D. To provide inadveretent payback - ✔✔A. To regulate control area interties



Studies have indicated that for a voltage reduction of 5%, non-motor loads, on average, will decrease by
what percentage?

A. 5%

B. 6.5%

C. 8%

D. 9.5% - ✔✔B. 6.5%

, What is a capacity benefit margin?

A. The unloaded and available on line generation capability

B. Transmission capacity set aside to back up the loss of generation

C. The amount of installed generation above the systems peak demand forecast

D. The amount of quick start generation capacity - ✔✔B. Transmission capacity set aside to back up the
loss of generation



Electric utilities must report major losses of firm system loads to which one of the following entities?

A. FERC

B. RCMP

C. DOE

D. EEI - ✔✔C. DOE



SMD (solar magnetic disturbance) may cause which of the following?

A. Relay operation

B. Transformer overheating

C. Transmission line de-rating

D. Frequency excursions - ✔✔B. Transformer overheating

(most likely primay result)



Area Interchange Error Surveys are conducted to improve which of the following?

A. Voltage stability

B. Frequency regulation

C. Economy of operation

D. Line overloads - ✔✔B. Frequency regulation



There is an inadvertent accumulation of +240 MWh (over generation) that should be used to schedule
exchange with a neighboring control area. If 50% is on peak, which schedule will work?

A. 10 MW received hour ending 1300 Saturday through hour ending 1200 Sunday (CST)

Geschreven voor

Instelling
NERC
Vak
NERC

Documentinformatie

Geüpload op
29 mei 2025
Aantal pagina's
32
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$7.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
InsightPapers

Maak kennis met de verkoper

Seller avatar
InsightPapers Havard School
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
4
Lid sinds
1 jaar
Aantal volgers
0
Documenten
489
Laatst verkocht
5 maanden geleden
edutech papers shop selling study exams elaborations :

High-quality exams and answers, summaries, exam guides, and practice questions created for top-performing students. Perfect for boosting your grades and preparing efficiently—organized by course and institution.

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen