PSM Certification Exam 1 (2025) Actual exam test|comprehensive
PSM Certification Exam 1
questions and verified answers| get it 100% ACCURATE!!
Study online at https://quizlet.com/_5qjz0h
1. Who's responsible for No one
Gantt Charts in Scrum?
Explanation
Gantt Chart is not a Scrum artifact and not compatible with the frame-
work.
2. Which statements are number 3 and 4
correct about Prod-
uct Backlog refinement? Explanation
(Choose 2 answers) If multiple teams are working on the project, they will participate in
1. should be done right the refinement as well. Refinement can take any amount of time from
before sprint planning the Product Owner but not more than 10% of the capacity of the
2. scrum master should Development Team.Refinement is a continuous activity not limited to
facilitate it a certain time during the Sprint. The Scrum Master only facilitates the
3. shouldnt take mroe meetings as requested or required; not by default.
than 10% of dev teams
time
4.multiple teams may
participate
3. The Product Owner has Point it out in the next sprint retro
doubts about the qual-
ity of the definition Explanation
of "Done". What should The Development Team is responsible for the definition of "Done"
s/he do? rather than the Product Owner. So, if the Product Owner doubts the
quality of the definition of "Done", he/she can discuss it with the team
on the next Sprint Retrospective, so that if they agree, it would be
adjusted for the next Sprint.
4. How long does the Sprint 8 hours for a one month sprint
Planning take in a project
with three-week Sprints? Explanation
, PSM Certification Exam 1
Study online at https://quizlet.com/_5qjz0h
Sprint Planning is 8 hours for a one-month Sprint and usually shorter
proportionally for shorter Sprints.
5. Which Scrum artifacts Product and Sprint Backlog
are ordered?
Explanation
The Product Backlog is ordered (prioritized) based on the business
value.The items in the Sprint Backlog follow the same order they had
in the Product Backlog, therefore, are prioritized.
6. Which of the following 2 and 4
describe the definition of
"Done"? (choose 2 an- Explanation
swers) Definition of "Done" increases transparency because everyone knows
what it means by "Done". It includes everything required for creating
1) Help increase velocity something usable by the end users (potentially releasable).
2) increases transparen-
cy
3) ensures everything is
documented
4) helps ensure the incre-
ment is releasable
7. Pick 4 activities that are 2,4,5,6
the responsibility of the
Development Team. Explanation
Designing the software is part of the development and should be done
1.) using Story Point esti- by the developers. They are self-organized and make technical deci-
mations sions and volunteer for tasks (assign them to themselves). Estimation
2.) Provide estimates is the responsibility of the developers because they are the people who
3.) breakdown epic user will develop the item.
stories into smaller ones
4.) design software
, PSM Certification Exam 1
Study online at https://quizlet.com/_5qjz0h
5.) make technical deci-
sions
6) volunteer for tasks
8. Which of the following Helping the Product owner find techniques for managing the product
is a valid service from backlog
the Scrum Master to the
Product Owner? Explanation
The following are the Scrum Master services to the Product Owner as
described in the Scrum Guide:-Finding techniques for effective Product
Backlog management;-Helping the Scrum Team understand the need
for clear and concise Product Backlog items;-Understanding product
planning in an empirical environment;-Ensuring the Product Owner
knows how to arrange the Product Backlog to maximize value;-Under-
standing and practicing agility;-Facilitating Scrum events as requested
or needed.-These are mainly focused on coaching/training, rather than
getting involved and helping someone do something.
9. When does inspection Frequently, but not so often that it gets in the way of the work
occur?
All Scrum events are opportunities for inspection and adaptation.In-
spection makes adaptation possible and that's why it's important. How-
ever, like anything else in Agile, we just like to have "enough" of it.
10. When is it time for inte- During the Sprint
grating the solution?
Explanation
Integration is part of the development of each item and a step in a
normal definition of "Done". Agile projects use continuous integration
to make the output potentially releasable.
11. Development Team
PSM Certification Exam 1
questions and verified answers| get it 100% ACCURATE!!
Study online at https://quizlet.com/_5qjz0h
1. Who's responsible for No one
Gantt Charts in Scrum?
Explanation
Gantt Chart is not a Scrum artifact and not compatible with the frame-
work.
2. Which statements are number 3 and 4
correct about Prod-
uct Backlog refinement? Explanation
(Choose 2 answers) If multiple teams are working on the project, they will participate in
1. should be done right the refinement as well. Refinement can take any amount of time from
before sprint planning the Product Owner but not more than 10% of the capacity of the
2. scrum master should Development Team.Refinement is a continuous activity not limited to
facilitate it a certain time during the Sprint. The Scrum Master only facilitates the
3. shouldnt take mroe meetings as requested or required; not by default.
than 10% of dev teams
time
4.multiple teams may
participate
3. The Product Owner has Point it out in the next sprint retro
doubts about the qual-
ity of the definition Explanation
of "Done". What should The Development Team is responsible for the definition of "Done"
s/he do? rather than the Product Owner. So, if the Product Owner doubts the
quality of the definition of "Done", he/she can discuss it with the team
on the next Sprint Retrospective, so that if they agree, it would be
adjusted for the next Sprint.
4. How long does the Sprint 8 hours for a one month sprint
Planning take in a project
with three-week Sprints? Explanation
, PSM Certification Exam 1
Study online at https://quizlet.com/_5qjz0h
Sprint Planning is 8 hours for a one-month Sprint and usually shorter
proportionally for shorter Sprints.
5. Which Scrum artifacts Product and Sprint Backlog
are ordered?
Explanation
The Product Backlog is ordered (prioritized) based on the business
value.The items in the Sprint Backlog follow the same order they had
in the Product Backlog, therefore, are prioritized.
6. Which of the following 2 and 4
describe the definition of
"Done"? (choose 2 an- Explanation
swers) Definition of "Done" increases transparency because everyone knows
what it means by "Done". It includes everything required for creating
1) Help increase velocity something usable by the end users (potentially releasable).
2) increases transparen-
cy
3) ensures everything is
documented
4) helps ensure the incre-
ment is releasable
7. Pick 4 activities that are 2,4,5,6
the responsibility of the
Development Team. Explanation
Designing the software is part of the development and should be done
1.) using Story Point esti- by the developers. They are self-organized and make technical deci-
mations sions and volunteer for tasks (assign them to themselves). Estimation
2.) Provide estimates is the responsibility of the developers because they are the people who
3.) breakdown epic user will develop the item.
stories into smaller ones
4.) design software
, PSM Certification Exam 1
Study online at https://quizlet.com/_5qjz0h
5.) make technical deci-
sions
6) volunteer for tasks
8. Which of the following Helping the Product owner find techniques for managing the product
is a valid service from backlog
the Scrum Master to the
Product Owner? Explanation
The following are the Scrum Master services to the Product Owner as
described in the Scrum Guide:-Finding techniques for effective Product
Backlog management;-Helping the Scrum Team understand the need
for clear and concise Product Backlog items;-Understanding product
planning in an empirical environment;-Ensuring the Product Owner
knows how to arrange the Product Backlog to maximize value;-Under-
standing and practicing agility;-Facilitating Scrum events as requested
or needed.-These are mainly focused on coaching/training, rather than
getting involved and helping someone do something.
9. When does inspection Frequently, but not so often that it gets in the way of the work
occur?
All Scrum events are opportunities for inspection and adaptation.In-
spection makes adaptation possible and that's why it's important. How-
ever, like anything else in Agile, we just like to have "enough" of it.
10. When is it time for inte- During the Sprint
grating the solution?
Explanation
Integration is part of the development of each item and a step in a
normal definition of "Done". Agile projects use continuous integration
to make the output potentially releasable.
11. Development Team