2024/2025 WITH ACTUAL QUESTIONS AND CORRECT
VERIFIED ANSWERS/ALREADY GRADED A+
UDC was required at time of installation for all systems installed after?
January 1, 2000
July 1, 2005, service techs shall possess or work under someone who has a
current certification indicating he or she has passed the?
ICC UST Service Technician Exam
ICC cert must be renewed every?
24 months
Service techs must possess or be employed by a person who has the
appropriate contractor's license unless?
The individual has a tank testing license
Service tech is defined by any individual who?
Tests UST monitoring equipment, trouble shoots UST systems, and/or installs
UST monitoring equipment.
,If the manufacturer training no longer exist, the local agency may?
Approve comparable alternate training .
UST includes?
Tank and connected piping
What is considered a UST?
A petroleum storage tank.
What UST system meets the requirements for secondary containment?
Doubled wall tanks
According to title 23; the following piping components if installed after July 1,
1987 must have secondary containment.
Pressured product piping
Considered "pipe" on tanks installed after July 1, 2003.
Pressured product piping and below ground vapor recovery.
,Under dispenser containment (UDC) was required for all existing UST systems
by
December 31, 2003
System for exchanging gas vapors in a storage tank and product in a fuel
delivery truck
Stage 1 vapor recovery
An approved method for non-visual monitoring for existing UST systems.
Statistical Inventory Reconciliation (SIR)
ATG must be capable for detecting a release of?
0.2 gallons per hour
What is no longer an approved method for non-visual monitoring on existing
UST systems?
Manual inventory reconciliation.
Automatic line leak detectors installed on underground piping with secondary
containment shall be capable of detecting a leak of ?
3 gallons per hour at 10 psi
, How often should ATG be programmed to test the tank?
At least monthly
According to PEI RP 300, a combustible gas can be used to?
Detect vapor leaks in a vapor recovery system.
According to PEI RP 300, a written scope of work for vapor recovery installation
should include?
Construction plans
Positive shut off overfill protection device must stop the flow of fuel when the
tank is no more then?
95% full
According to Executive Order (EO) VR 201-A , what could cause a nozzle shut
off mechanism or malfunction?
Depended filter seal damage
According to VR 201-A, breakaway reconnection must be?