ICC GENERAL REQUIREMENTS PRACTICE
EXAM 2025| BRAND NEW ACTUAL EXAM WITH
100% VERIFIED QUESTIONS AND CORRECT
ANSWERS| GUARANTEED VALUE PACK| ACE
YOUR GRADES.
Who performs a structural observation?
A) the RDP in responsible charge
B) The special inspector
C) The contractor
D) The building official - Correct Answer-A) the RDP in responsible charge
Who prepares the statement of special inspections?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Correct Answer-D) The RDP
Who is in charge of reviewing and approving reports?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Correct Answer-D) The RDP
, Page |2
ICC exams are based on which document?
a) ACI
b) IBC
c) ASTM - Correct Answer-B) IBC
Who is in charge of giving "approval to proceed"
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Correct Answer-A
Who responds to reports of uncorrected discrepancies?
A) The building official
B) the contractor
C) The owner
D) The RDP - Correct Answer-D) The RDP
What does a special inspector's job NOT entail while on the job site?
A) instructing the contractor;s workers on how to do their job