According to the Model Program for Special Inspection, the special inspector is to
prepare written report of inspection: - CORRECT ANSWER-After each inspection
visit - Section II B 5 - Model Programs
According to the Model Program for Special Inspection, which of the following
items does not need to be included in each inspection report? - CORRECT
ANSWER-Description of discussions with the contractor - Section B 5 - Model
Programs
According to the Specification for Structural Joints using high strength bolts, the
nominal diameter of standard bolt holes shall be how much larger than the
nominal bolt diameter? - CORRECT ANSWER-1/16 inch - Specification for
Structural Joints Table 3.1
Discrepancies in the work shall be brought to the immediate attention of the
"blank" for corrective action. - CORRECT ANSWER-the contractor - 2009 IBC,
Section 1704.1.2.
,The special inspector shall furnish inspection reports to the "blank" and to the
"blank"? - CORRECT ANSWER-Building Official and Registered Design
professional
The special inspector shall provide continuos inspection of: - CORRECT
ANSWER-Single-pass fillet welds greater than 5/16 inch in size - 2099 IBC, Table
1704.3, Item 5.3
The special inspections required by this code are not required where the work is
done on the premise of a? - CORRECT ANSWER-Approved fabricator - 2009 IBC,
Section 1704.2.2
The special inspection of the steel fabrication process shall not be required where
the fabricator does not perform any? - CORRECT ANSWER-heating operations -
2009 IBC, Section 1704.3, Exceptions # 1
According to the IBC, the "blank" is to hire the special inspector. - CORRECT
ANSWER-owner or owners agent. 2009 IBC Section 1704.1
According to the IBC, the "blank" is the responsible for the approval of a person's
qualifications to act as a special inspector. - CORRECT ANSWER-code official.
2009 IBC, Section 1704.1
According to the IBC, discrepancy corrections are made known to the building
official by: - CORRECT ANSWER-final report. 2009 IBC, Section1704.1.2
, When is the code official to be made aware of a discrepancy found during a
special inspection? - CORRECT ANSWER-If it is not corrected by the contractor.
2009 IBC, Section 1704.1.2
According to the Model Program for Special Inspection, the special inspector is to
document work that is nonconforming: - CORRECT ANSWER-In a written report
- Section II B 4 - Model Programs
According to the Specifications for Structural Steel Buildings, ASTM Standard
"blank" is to be used for the material test for steel sheets. - CORRECT ANSWER-
A568 - Section A31, Specifications for Structural Steel Buildings
According to the Specifications for Structural Steel Buildings, the "blank" conducts
the material tests for identification of the structural steel. - CORRECT ANSWER-
Fabricator or Testing Laboratory - Section A31, Specifications for Structural Steel
Buildings.
According to the Specifications for Structural Steel Buildings, which of the
following steel members are allowed to be unidentified steel? - CORRECT
ANSWER-Unimportant members, where their physical properties and weldability
would not affect the structure strength - Section A31b, Specifications for
Structural Steel Buildings
According to the Code of Standard Practice for Steel Buildings and Bridges, how is
steel of special material to be identified? - CORRECT ANSWER-It is marked by
the supplier - Section 5.1.1, Code of Standard Practice for Steel Buildings and
Bridges