Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

CSLB Concrete C8 License Practice Test #4 Questions And Answers Verified 100% Correct

Rating
-
Sold
-
Pages
13
Grade
A+
Uploaded on
01-06-2025
Written in
2024/2025

CSLB Concrete C8 License Practice Test #4 Questions And Answers Verified 100% Correct What is the unit of concrete quantity take-off? - ANSWER Cubic feet Which of the following concrete pouring strategies is commonly adopted while filling stair steps? - ANSWER From bottom to top How much water needs to be added to the concrete to increase the slump value of a cubic yard of concrete by one unit? - ANSWER One gallon Which of the following factors increases the drying shrinkage as well as creeping in concrete structures ? - ANSWER Low Temperature & Low Relative Humidity Which of the following are three major types of concrete project cost estimates that are commonly used in the project planning? - ANSWER Preliminary Estimate, Detailed Estimate, Engineer's Estimate Explanation: Preliminary estimate is general conceptual estimate based on the conceptual design of a project. Detailed estimate is based on the detailed scope of work of the project. Engineer's estimate is the final estimate based on the project specifications and plans. What is the recommended curing time for a normal concrete between 50°F to 70°F? - ANSWER 7 Days Explanation: After 7 days, concrete will be able to withstand heavier loads, however, heavy machinery should still be kept away from the concrete. Foundation false-work is commonly done with the help of: - ANSWER Piling or Mudsill Which of the following statements about structural and non-structural concrete is correct? - ANSWER Non - structural c oncrete uses lightweight concrete only What is the recommended waste ratio for ready mixed concrete commonly adopted in the industry? - ANSWER 7.3% What is the standard weight of cement, sand, and aggregate, respectively, that will be required to make one cubic feet of fresh concrete of 1:2:3 ratios? - ANSWER 22 pounds, 41 pounds, 70 pounds What is the recommended wastage ratio considered for estimating the heavy weight reinforcing steel bars of #30 or above for a concrete construction project? - ANSWER 3.3 percent What is the recommended ratio of wastage for formwork commonly used in the concrete construction industry? - ANSWER 25 percent How many square inches are there in a square foot of area? - ANSWER 144 square inches The drying shrinkage of concrete is independent of _____________in the concrete, as concrete dries up during the setting time. - ANSWER Stress Which of the following tests are recommended by ASTM C94 standard to verify the quality of ready mixed concrete while pouring it in the structural forms? - ANSWER Temperature Test, Air Content Test, Slump Test How many take-off methods are commonly used for concrete estimating activity in the industry? - ANSWER 3 Explanation: There are three take-off methods commonly used for concrete take-off needs. UnitTake-off Perimeter Take-off Centerline Take-off Which of the following cost estimate methodologies is commonly used in a concrete construction planning project? - ANSWER Unit Cost Method Explanation: The unit method is the more practical approach because it uses an operational unit as the base of cost. This cost includes each and every factor required to complete an operational unit. So, the accuracy of this method is based on practical work of the same type. The ratio of cement, sand, aggregate, and water to prepare fresh/wet concrete is defined in terms of ________ not ________. - ANSWER Weight & Volume Which of the following ratios of moisture is recommended in a soil or granular layer to achieve the best quality of compaction? - ANSWER 12 percent Which of the following options is NOT a structural concrete element? - ANSWER ALL -Statuary -Cornices -Corbels Which of the following pieces of equipment is commonly used for small project concrete floating to give a finished look? - ANSWER Darby Which of the following statements is true about concrete swelling in humid or wet conditions? - ANSWER Swelling takes longer periods , ranging from 6 to 12 months

Show more Read less
Institution
CSLB Concrete C8 License
Course
CSLB Concrete C8 License

Content preview

CSLB Concrete C8 License Practice Test #4 Questions
And Answers Verified 100% Correct


What is the unit of concrete quantity take-off? - ANSWER Cubic feet

Which of the following concrete pouring strategies is commonly adopted while
filling stair steps? - ANSWER From bottom to top

How much water needs to be added to the concrete to increase the slump value of
a cubic yard of concrete by one unit? - ANSWER One gallon

Which of the following factors increases the drying shrinkage as well as creeping
in concrete structures ? - ANSWER Low Temperature & Low Relative Humidity

Which of the following are three major types of concrete project cost estimates
that are commonly used in the project planning? - ANSWER Preliminary Estimate,
Detailed Estimate, Engineer's Estimate

Explanation:
Preliminary estimate is general conceptual estimate based on the conceptual
design of a project.
Detailed estimate is based on the detailed scope of work of the project.
Engineer's estimate is the final estimate based on the project specifications and
plans.

What is the recommended curing time for a normal concrete between 50°F to
70°F? - ANSWER 7 Days

Explanation:
After 7 days, concrete will be able to withstand heavier loads, however, heavy
machinery should still be kept away from the concrete.

, Foundation false-work is commonly done with the help of: - ANSWER Piling or
Mudsill

Which of the following statements about structural and non-structural concrete is
correct? - ANSWER Non - structural c oncrete uses lightweight concrete only

What is the recommended waste ratio for ready mixed concrete commonly
adopted in the industry? - ANSWER 7.3%

What is the standard weight of cement, sand, and aggregate, respectively, that will
be required to make one cubic feet of fresh concrete of 1:2:3 ratios? - ANSWER 22
pounds, 41 pounds, 70 pounds

What is the recommended wastage ratio considered for estimating the heavy
weight reinforcing steel bars of #30 or above for a concrete construction project? -
ANSWER 3.3 percent

What is the recommended ratio of wastage for formwork commonly used in the
concrete construction industry? - ANSWER 25 percent

How many square inches are there in a square foot of area? - ANSWER 144
square inches

The drying shrinkage of concrete is independent of _____________in the
concrete, as concrete dries up during the setting time. - ANSWER Stress

Which of the following tests are recommended by ASTM C94 standard to verify
the quality of ready mixed concrete while pouring it in the structural forms? -
ANSWER Temperature Test, Air Content Test, Slump Test

How many take-off methods are commonly used for concrete estimating activity
in the industry? - ANSWER 3

Explanation:
There are three take-off methods commonly used for concrete take-off needs.

Written for

Institution
CSLB Concrete C8 License
Course
CSLB Concrete C8 License

Document information

Uploaded on
June 1, 2025
Number of pages
13
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$10.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TopGradeGuru Teachme2-tutor
Follow You need to be logged in order to follow users or courses
Sold
15
Member since
1 year
Number of followers
0
Documents
2395
Last sold
2 months ago
GRADEHUB

We provide access to a wide range of professionally curated exams for students and educators. It offers high-quality, up-to-date assessment materials tailored to various subjects and academic levels. With instant downloads and affordable pricing, it\'s the go-to resource for exam preparation and academic success.

1.5

2 reviews

5
0
4
0
3
0
2
1
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions