EBOLC Demolition Exam Questions And Answers Verified 100% Correct What's a booster? - ANSWER- High strength blasting cap with an internal charge How do you tie in a branch line to a ring main or line main? - ANSWER- girth hitch with a extra turn How do you connect M151/M152 to a ring main or line main? - ANSWER- J-hook with an extra loop How long is the tail on det cord after it's tied off? - ANSWER- 6" inches Knot type to prime C4 in cold temperatures - ANSWER- Uli Knot Knot type to prime C4 in warm or cold temperatures - ANSWER- double over hand knot 6 Steps for calculating total amount of explosives - ANSWER- 1)Identify & measure the critical dimensions 2)Calculate using explosive formula or Use Rule of Thumb (ROT) *If you have ROT in step 2, ignore step 3 3)Divide by the RE Factor 4)Divide by package weight/volume (round up) 5) Calculate for number of charges 6)Calculate for total amount of explosives External Timber Cutting Charge Formula - ANSWER- P= (D^2)/40 P=Pounds of explosive per target D=Diameter Four Formula types for Charges *Just for exam - ANSWER- 1)External Timber Cutting Charge 2)Stump Removal 3)Block Charge 4)Ribbon Charge (We will be tested on this more than likely) Block Charge - ANSWER- P=(0.375)*A P=Pounds of explosive A=area of cross section in square 0.375=constant Stump Removal Rules of Thumb - ANSWER- 1)Dead Stump: 1 pound per foot of diameter 2)Live Stump: 2 pounds per foot of diameter 3) Standing Tree: 3 pounds per foot of diameter *Convert Circumference to diameter Note: Measurements are taken 12 to 18 inches above the ground Special Steel Cutting Charges Rule of Thumb - ANSWER- 1) Charge Thickness= 0.5 Target Thickness but never less than 0.5 inch 2) Charge width= 3 times the charge thickness 3)Charge length= length of target thickness to be cut *Divide by 20cu volume for C4 instead of 1.25 package weight Formula Based Flowchart - ANSWER- Data Formula RE factor Package Weight No. Targets Targets x Package = TOTAL Rule of Thumb Flowchart - ANSWER- Data Rule Of Thumb NA Package Weight No. Targets Targets x Package = TOTAL External Timber Formula - ANSWER- P=D^2 / 40 Stump Removal ROT - ANSWER- Dead: 1 lb charge per foot Alive Stump: 2 lb charge per foot Standing Tree: 3 lb charge per foot Circumference to Diameter - ANSWER- C / 3.14 = D Ring Charge - ANSWER- P= D^2 / 40 Block Charge Formula - ANSWER- P=0.375 x A Aria of an 'I' Beam formula - ANSWER- A = (tW x tH)+(wW x wH)+(bW x bH) Ribbion Charge ROT - 'I' Beam - ANSWER- Charge Thickness = .5 of target Thickness Charge Width = 3 x Charge Thickness Charge Length = Length of Target Ribbion Charge Calculation Set up - ANSWER- TF: T x W x L = TF W: T x W x L = W BF: T x W x L = BF BF+W+TF= Volume Width to Length at 45 degrees - ANSWER- Width x 1.414 = length Hasty road crater rule of thumbs - ANSWER- 10 lb : 1' depth Number of holes for hasty - ANSWER- N = L - 16 / 5 +1 Line six hasty - ANSWER- Number of holes (explosives 1 + explosives 2) Cratering flowchart - ANSWER- Data / find length ROT (wt. Per Hole) NA Package Weight Number of Holes Formula Total number of explosives per type Deliberate Crater ROT - ANSWER- 7' = 80 Lb 5' = 40 Lb Breaching Formula - ANSWER- P = R^3 x K x C Number of charges for Breeching charge - ANSWER- N = R/2R Counterforce Charge - ANSWER- 1.5 lb : d' Breaching a hard surface - ANSWER- .5 lb : target x 1" M11 (Cap Type/ Length) - ANSWER- High Strength/ 30 ft M12 (Cap Type/Length) - ANSWER- Low Strength/ 500ft M13 (Cap Type/Length) - ANSWER- Low Strength/ 1000ft M14 (Cap Type/Length) - ANSWER- High Strength/7.5ft M18 (Cap Type/Length) - ANSWER- High Strength/ 30ft M19 (Cap Type/Length) - ANSWER- High Strength/ 200ft

Meer zien Lees minder
Instelling
EBOLC Demolition
Vak
EBOLC Demolition

Voorbeeld van de inhoud

EBOLC Demolition Exam Questions And
Answers Verified 100% Correct
What's a booster? - ANSWER- High strength blasting cap with an internal charge

How do you tie in a branch line to a ring main or line main? - ANSWER- girth hitch with
a extra turn

How do you connect M151/M152 to a ring main or line main? - ANSWER- J-hook with
an extra loop

How long is the tail on det cord after it's tied off? - ANSWER- 6" inches

Knot type to prime C4 in cold temperatures - ANSWER- Uli Knot

Knot type to prime C4 in warm or cold temperatures - ANSWER- double over hand knot

6 Steps for calculating total amount of explosives - ANSWER- 1)Identify & measure the
critical dimensions
2)Calculate using explosive formula or Use Rule of Thumb (ROT)
*If you have ROT in step 2, ignore step 3
3)Divide by the RE Factor
4)Divide by package weight/volume (round up)
5) Calculate for number of charges
6)Calculate for total amount of explosives

External Timber Cutting Charge Formula - ANSWER- P= (D^2)/40
P=Pounds of explosive per target
D=Diameter

Four Formula types for Charges
*Just for exam - ANSWER- 1)External Timber Cutting Charge
2)Stump Removal
3)Block Charge
4)Ribbon Charge (We will be tested on this more than likely)

Block Charge - ANSWER- P=(0.375)*A
P=Pounds of explosive
A=area of cross section in square
0.375=constant

Stump Removal Rules of Thumb - ANSWER- 1)Dead Stump: 1 pound per foot of

, diameter
2)Live Stump: 2 pounds per foot of diameter
3) Standing Tree: 3 pounds per foot of diameter
*Convert Circumference to diameter
Note: Measurements are taken 12 to 18 inches above the ground

Special Steel Cutting Charges Rule of Thumb - ANSWER- 1) Charge Thickness= 0.5
Target Thickness but never less than 0.5 inch
2) Charge width= 3 times the charge thickness
3)Charge length= length of target thickness to be cut
*Divide by 20cu volume for C4 instead of 1.25 package weight

Formula Based Flowchart - ANSWER- Data
Formula
RE factor
Package Weight
No. Targets
Targets x Package = TOTAL

Rule of Thumb Flowchart - ANSWER- Data
Rule Of Thumb
NA
Package Weight
No. Targets
Targets x Package = TOTAL

External Timber Formula - ANSWER- P=D^

Stump Removal ROT - ANSWER- Dead: 1 lb charge per foot
Alive Stump: 2 lb charge per foot
Standing Tree: 3 lb charge per foot

Circumference to Diameter - ANSWER- C / 3.14 = D

Ring Charge - ANSWER- P= D^

Block Charge Formula - ANSWER- P=0.375 x A

Aria of an 'I' Beam formula - ANSWER- A = (tW x tH)+(wW x wH)+(bW x bH)

Ribbion Charge ROT - 'I' Beam - ANSWER- Charge Thickness = .5 of target Thickness
Charge Width = 3 x Charge Thickness
Charge Length = Length of Target

Geschreven voor

Instelling
EBOLC Demolition
Vak
EBOLC Demolition

Documentinformatie

Geüpload op
5 juni 2025
Aantal pagina's
5
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$9.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TopGradeGuru Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
15
Lid sinds
1 jaar
Aantal volgers
0
Documenten
2399
Laatst verkocht
4 weken geleden
GRADEHUB

We provide access to a wide range of professionally curated exams for students and educators. It offers high-quality, up-to-date assessment materials tailored to various subjects and academic levels. With instant downloads and affordable pricing, it\'s the go-to resource for exam preparation and academic success.

1.5

2 beoordelingen

5
0
4
0
3
0
2
1
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen