Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

NCCCO MOBILE CRANE EXAM|| ACTUAL EXAM ALL QUESTIONS AND 100% CORRECT ANSWERS ALREADY GRADED A+|| LATEST AND FULLY COVERED VERSION WITH VERIFIED SOLUTIONS|| ASSURED PASS!!

Beoordeling
-
Verkocht
-
Pagina's
20
Cijfer
A+
Geüpload op
08-06-2025
Geschreven in
2024/2025

NCCCO MOBILE CRANE EXAM|| ACTUAL EXAM ALL QUESTIONS AND 100% CORRECT ANSWERS ALREADY GRADED A+|| LATEST AND FULLY COVERED VERSION WITH VERIFIED SOLUTIONS|| ASSURED PASS!! 1. What action does a signal person intend the operator to perform if he extends his arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up? a. Boom down b. Swing c. Boom up d. Extend boom - ANSWER: c. 2. When hoisting personnel, within what percentage of level must a telescopic boom crane be in order for the gross ratings in the load chart to remain valid? a. 1% b. 2% c. 5% d. 8% - ANSWER: a. 3. The load line of the crane you're operating contacts an energized power line. There's no sign of any other danger, such as fire. What should you do? a. Climb down carefully from the crane cab b. Jump down, feet together c. Stay in the cab until the lines are de-energized d. Get as far away from the crane as possible - ANSWER: c.2 | P a g e 4. According to OSHA 1926.1413, how many randomly distributed broken wires in rotation-resistant rope are cause for replacement of the rope? a. 1 broken wire in 6 rope diameters b. 2 broken wires in 30 rope diameters c. 3 broken wires in one strand in one lay d. 2 broken wires in 6 rope diameters - ANSWER: d. 5. What is the net capacity of a crane on main boom unless the manufacturer states otherwise? a. The capacity listed in the load chart minus the weight of the rigging and all attachments b. The capacity listed in the load chart plus the weight of the rigging and all attachments c. The capacity listed in the load chart minus the weight of the rigging and all attachments not in use d. The capacity listed in the load chart minus the weight of the rigging alone - ANSWER: a

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

1|Page



NCCCO MOBILE CRANE EXAM|| ACTUAL EXAM
ALL QUESTIONS AND 100% CORRECT ANSWERS
ALREADY GRADED A+|| LATEST AND FULLY
COVERED VERSION 2024-2025 WITH VERIFIED
SOLUTIONS|| ASSURED PASS!!
1. What action does a signal person intend the operator to perform if he extends his
arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up?
a. Boom down
b. Swing
c. Boom up
d. Extend boom - ANSWER: c.


2. When hoisting personnel, within what percentage of level must a telescopic
boom crane be in order for the gross ratings in the load chart to remain valid?
a. 1%
b. 2%
c. 5%
d. 8% - ANSWER: a.


3. The load line of the crane you're operating contacts an energized power line.
There's no sign of any other danger, such as fire. What should you do?
a. Climb down carefully from the crane cab
b. Jump down, feet together
c. Stay in the cab until the lines are de-energized
d. Get as far away from the crane as possible - ANSWER: c.

,2|Page


4. According to OSHA 1926.1413, how many randomly distributed broken wires in
rotation-resistant rope are cause for replacement of the rope?
a. 1 broken wire in 6 rope diameters
b. 2 broken wires in 30 rope diameters
c. 3 broken wires in one strand in one lay
d. 2 broken wires in 6 rope diameters - ANSWER: d.


5. What is the net capacity of a crane on main boom unless the manufacturer states
otherwise?
a. The capacity listed in the load chart minus the weight of the rigging and all
attachments
b. The capacity listed in the load chart plus the weight of the rigging and all
attachments
c. The capacity listed in the load chart minus the weight of the rigging and all
attachments not in use
d. The capacity listed in the load chart minus the weight of the rigging alone -
ANSWER: a.


6. What may happen to a properly rigged load when lifted off the ground unless the
operator takes account of boom deflection?
a. It could swing out away from the crane
b. It could swing in towards the crane
c. It could raise absolutely vertically
d. It could shift in its rigging - ANSWER: a.


7. What Standard Method hand signal is being illustrated?


a. Swing

, 3|Page


b. Stop
c. Emergency Stop
d. Travel - ANSWER: a.


8. Who should an operator respond to a "stop" signal from?
a. Appointed signal person only
b. Project manager only
c. Superintendent only
d. Anyone - ANSWER: d.


9. Which area do truck cranes without a 5th outrigger generally have no lifting
capacity unless the manufacturer states otherwise?
a. The side
b. The rear
c. The front
d. The outriggers - ANSWER: c.


10. What is the definition of "operating radius?"
a. The distance from the base of the boom to the center of the load b. The distance
from the front of the crane to the center of gravity of the load
c. The distance from the center of rotation of the crane to the center of the load
d. The distance from the center of rotation of the crane to the center of gravity of
the load - ANSWER: d.


11. What applies to the capacities below the bold line shown on a load chart?
a. They are based on the structural strength of the crane

Geschreven voor

Vak

Documentinformatie

Geüpload op
8 juni 2025
Aantal pagina's
20
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$13.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
NurseAdvocate chamberlain College of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
498
Lid sinds
2 jaar
Aantal volgers
77
Documenten
12043
Laatst verkocht
16 uur geleden
NURSE ADVOCATE

I have solutions for following subjects: Nursing, Business, Accounting, statistics, chemistry, Biology and all other subjects. Nursing Being my main profession line, I have essential guides that are Almost A+ graded, I am a very friendly person: If you would not agreed with my solutions I am ready for refund

4.5

238 beoordelingen

5
191
4
14
3
16
2
6
1
11

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen