When first arriving on a jobsite the operator should first
determine the condition of the - ✔✔✔ Correct Answer > Crane
setup location
How does the operator verify the LMI boom length or load
radius reading - ✔✔✔ Correct Answer > Actual measurements
If the rated capacity of the crane is above the solid line or
within the shaded areas or has an asterisk next to it, this means
the capacity is based on: - ✔✔✔ Correct Answer > Structural
competence
All hazards and potential problems should be discovered during
the - ✔✔✔ Correct Answer > Pre-lift site inspection
, How many broken wires must be present in one strand of one
lay for running wire rope to be removed from service? - ✔✔✔
Correct Answer > 3
In a range diagram boom length and angle can be used to
determine ? - ✔✔✔ Correct Answer > Load radius
The primary effect of eccentric main boom tip reeving is - ✔✔✔
Correct Answer > Twisting of the boom
How many randomly broken wires in one rope lay must there
be to remove a 6x37 running wire rope from service? - ✔✔✔
Correct Answer > 6
When lifting personnel in a manbasket using 6x19 wire rope,
the minimum safety factor is ? - ✔✔✔ Correct Answer > 7
What is the safety factor required when using non rotating wire
rope and lifting personnel in a manbasket ? - ✔✔✔ Correct
Answer > 10