Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

NERC Practice Test Questions with complete solutions 2025

Rating
-
Sold
-
Pages
20
Grade
A+
Uploaded on
09-06-2025
Written in
2024/2025

NERC Practice Test Questions with complete solutions 2025 A .transmission .line .is .operating .with .a .voltage .phase .angle .different .of .30 .degrees .between .the .sending .Vs .and .the .receiving .bus .Vr. .If .the .receiving .end .load .is .suddenly .increased, .the .voltage .phase .angle .difference .will .be? .- .ANS -The .phase .angle .will .increase. .When .load .is .increased .phase .angle .will .increase. A .load .has .a .power .factor .of .0.9 .lagging. .If .the .load .draws .100 .MVA, .what .is .the .MW .draw? .- .ANS -90 .pf= .mw/mva The .high .side .of .a .delta-wye .connection .transformer .is .connected .to .a .power .system .with .199 .kV .L-G .high .side .voltage. .What .is .the .voltage .across .the .delta .winding .of .the .transformer? .- .ANS -Vl-l= .square .root .of .3 .times .Vl-g .1.73x191= .345kV If .a .transmission .line .is .carrying .400 .MW .and .300 .MVAR .what .is .the .MVA? .- .ANS -3-4-5 .triangle .500 .MVA The .prime .mover .is .the .component .of .the .generator .that .creates .the .rotational .force. .In .a .typical .coal .fired .steam .generator .what .component .spins .the .rotor? .- .ANS -Turbine Reactive .reserve .response .during .a .disturbance .is .best .obtained .from .which .devise? .- .ANS -Synchronous .condensers For .two .identically .constructed .transmission .lines .where .Line .A .is .150 .miles .long .and .line .B .is .15 .miles .long, .if .both .lines .are .lightly .loaded? .- .ANS -A .produces .more .reactive .power .than .B. Lightly .loaded .transmission .lines .essentially .behave .like? .- .ANS -Shunt .Capacitors You .receive .an .alarm .that .indicates .low .oil .pressure .on .an .underground .transmission .cable. .SCADA .shows .the .pressure .is .continuing .to .drop. .What .is .the .first .step .you .take .to .protect .the .line? .- .ANS -Isolate .the .line Computer .simulations .show .that .for .a .100 .MW .schedule .from .Bus .A .to .Bus .B, .63% .of .the .schedule .will .flow .on .the .scheduled .path .and .the .remainder . .on .other .parallel .paths. .What .is .the .distribution .factor .for .the .scheduled .path? .- .ANS -63% Which .statement .best .describes .how .reactive .power .MVAR .power .normally .flows? .- .ANS -High .Voltage .to .Low .Voltage Which .of .the .following .types .of .data .are .BA .and .RC .not .required .to .share .with .one .another? .- .ANS -Generator .start .up .cost TOP .must .develop, .maintain, .and .implement .formal .policies .and .procedures .to .provide .for .transmission .reliability. .Which .of .the .following .DOES .NOT .need .to .be .addressed .in .these .policies .and .procedures? .- .ANS -Planned .outages .of .generation .units A .1000 .MVA .rated .generator .that .produces .800 .MW .and .100 .MVAR .is .best .described .as? .- .ANS -Opera

Show more Read less
Institution
Course

Content preview

NERC Practice Test Questions with
complete solutions 2025



A .transmission .line .is .operating .with .a .voltage .phase .angle .different .of .30
.degrees .between .the .sending .Vs .and .the .receiving .bus .Vr. .If .the .receiving .end
.load .is .suddenly .increased, .the .voltage .phase .angle .difference .will .be? .- .ANS✓
✓-The .phase .angle .will .increase. .When .load .is .increased .phase .angle .will
.increase.


A .load .has .a .power .factor .of .0.9 .lagging. .If .the .load .draws .100 .MVA, .what .is
.the .MW .draw? .- .ANS✓✓-90 .pf= .mw/mva


The .high .side .of .a .delta-wye .connection .transformer .is .connected .to .a .power
.system .with .199 .kV .L-G .high .side .voltage. .What .is .the .voltage .across .the .delta
.winding .of .the .transformer? .- .ANS✓✓-Vl-l= .square .root .of .3 .times .Vl-g
.1.73x191= .345kV


If .a .transmission .line .is .carrying .400 .MW .and .300 .MVAR .what .is .the .MVA? .-
.ANS✓✓-3-4-5 .triangle .500 .MVA


The .prime .mover .is .the .component .of .the .generator .that .creates .the .rotational
.force. .In .a .typical .coal .fired .steam .generator .what .component .spins .the .rotor?
.- .ANS✓✓-Turbine


Reactive .reserve .response .during .a .disturbance .is .best .obtained .from .which
.devise? .- .ANS✓✓-Synchronous .condensers


For .two .identically .constructed .transmission .lines .where .Line .A .is .150 .miles
.long .and .line .B .is .15 .miles .long, .if .both .lines .are .lightly .loaded? .- .ANS✓✓-A
.produces .more .reactive .power .than .B.


Lightly .loaded .transmission .lines .essentially .behave .like? .- .ANS✓✓-Shunt
.Capacitors


You .receive .an .alarm .that .indicates .low .oil .pressure .on .an .underground
.transmission .cable. .SCADA .shows .the .pressure .is .continuing .to .drop. .What .is
.the .first .step .you .take .to .protect .the .line? .- .ANS✓✓-Isolate .the .line


Computer .simulations .show .that .for .a .100 .MW .schedule .from .Bus .A .to .Bus .B,
.63% .of .the .schedule .will .flow .on .the .scheduled .path .and .the .remainder .will

,.flow .on .other .parallel .paths. .What .is .the .distribution .factor .for .the .scheduled
.path? .- .ANS✓✓-63%


Which .statement .best .describes .how .reactive .power .MVAR .power .normally
.flows? .- .ANS✓✓-High .Voltage .to .Low .Voltage


Which .of .the .following .types .of .data .are .BA .and .RC .not .required .to .share .with
.one .another? .- .ANS✓✓-Generator .start .up .cost


TOP .must .develop, .maintain, .and .implement .formal .policies .and .procedures .to
.provide .for .transmission .reliability. .Which .of .the .following .DOES .NOT .need .to
.be .addressed .in .these .policies .and .procedures? .- .ANS✓✓-Planned .outages .of
.generation .units


A .1000 .MVA .rated .generator .that .produces .800 .MW .and .100 .MVAR .is .best
.described .as? .- .ANS✓✓-Operating .in .a .lagging .mode. .Inductive .system


Which .of .the .following .types .of .MW .load .is .the .most .impacted .by .an .intentional
.frequency .reduction? .- .ANS✓✓-Motor


Assume .there .are .two .250 .mile .long .transmission .lines .exporting .an .excessive
.amount .of .MW .from .a .generation .area .to .a .load .area. .One .of .the .lines .suddenly
.trips .and .the .area .power .system .collapses .within .a .few .seconds. .The .most
.likely .cause .of .the .collapse? .- .ANS✓✓-Angle .Instability


The .phase .voltage .in .a .wye-connected .load .is .277 .V. .What .is .the .line .to .line
.voltage? .- .ANS✓✓-480 .V


A .simple .power .system .is .composed .of .three .lines .connecting .generation .to
.load. .Each .lines .the .same .impedance, .is .initially .loaded .at .200 .MW, .and .has .a
.thermal .limit .of .400 .MW. .If .one .line .trips, .what .the .loading .on .the .shortest
.remaining .line .be .and .will .the .thermal .limit .either .remaining .line .be .violated? .-
.ANS✓✓-300 .MW .and .No


The .best .prediction .of .system .load .is .the .load .forecast .tool .that .uses? .- .ANS✓
✓-Forecasted .Weather

If .the .phase .angel .at .an .open .breaker .is .equal .to .1/10 .of .a .cycle, .this .is .the .the
.same .angle .as? .- .ANS✓✓-1/10 .of .360 .so .36


A .___________ .tool .is .used .to .ensure .the .power .system .can .respond .within
.acceptable .limits .of .N-1 .- .ANS✓✓-Contingency .Analysis


Which .of .the .following .activities .would .not .be .included .in .the .procedures .for
.transmission .reliability? .- .ANS✓✓-Ancillary .service .pricing

, The .transmission .Operator .and .BA .shall .provide .documentation .that .operating
.personnel .have .______ .to .implement .real .time .actions .to .ensure .the .stable .and
.reliable .operation .of .the .BES. .- .ANS✓✓-Proper .NERC .Certification .Credential


A .utility .distribution .bus .has .the .following .customer .loads .attached. .What .is
.the .total .customer .MW .load .and .is .the .total .customer .load .capacitive .or
.inductive? .5 .MW .1 .MVAR .& .3 .MW .1 .MVAR .& .2 .MW .-2 .MVAR .& .10 .MW .3 .MVAR
.- .ANS✓✓-20 .mw .and .Inductive


How .many .MVARs .does .a .230 .kV, .50 .MVAR .capacitor .bank .provide .when .the
.voltage .id .207 .kV .- .ANS✓✓-Actual .MW/ .Rated .MW .^2 .x .Capacitor .Rating
40

You .are .a .system .operator .and .the .load .forecast .is .for .an .all .time .summer .peak
.load .day, .generations .and .reactive .resources .will .be .tight. .Which .scheduled .job
.would .you .allow .to .proceed? .- .ANS✓✓-735 .kV .shunt .reactor .maintenance.


A .contingency .results .in .the .exceedance .of .an .IROL. .What .could .be .the .result
.if .the .IROL .is .allowed .to .be .exceeded .longer .than .T .sub .v .- .ANS✓✓-
Interruption .of .power .to .a .large .part .of .the .BES

Generators .have .the .ability .to .be .used .as .voltage .control .devices. .If .a .generator
.raises .its .VAR .output, .the .system .orator .should .expect .system .stage .to? .- .ANS
✓✓-Increase

The .actual .voltage .is .362kV .on .a .345 .bus. .What .is .the .p.u. .voltage? .- .ANS✓✓-
1.05

In .the .initial .stages .of .a .system .restoration .condition .high .transmission .system
.voltage .problems .are .more .likely .than .low .transmission .system .voltage
.problems .why? .- .ANS✓✓-Because .of .excessive .MVAR .supply .from .the
.energization .of .transmission .lines


All .transmission .operators .shall .operate .so .that .instability .uncontrolled
.separation .or .cascading .outages .will .not .occur .in .result .of? .- .ANS✓✓-Most
.severe .single .contingency .MSSC


A .230kV .transmission .line .is .energized .at .230kV .and .is .100 .miles .long. .What .is
.the .approximate .line .charging .contribution? .- .ANS✓✓-30MVAR


When .the .system .is .on .the .verge .of .a .voltage .collapse .and .nothing .else .can .be
.done .to .alleviate .the .problem, .operating .personnel .should? .- .ANS✓✓-Shed
.Load


The .transmission .operator .shall .take .corrective .actions .necessary .to .prevent
.voltage .collapse .when .reactive .resources .are .insufficient .including? .- .ANS✓✓-
Shedding .Load

Written for

Course

Document information

Uploaded on
June 9, 2025
Number of pages
20
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$13.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
NurseAdvocate chamberlain College of Nursing
Follow You need to be logged in order to follow users or courses
Sold
490
Member since
2 year
Number of followers
76
Documents
12046
Last sold
23 hours ago
NURSE ADVOCATE

I have solutions for following subjects: Nursing, Business, Accounting, statistics, chemistry, Biology and all other subjects. Nursing Being my main profession line, I have essential guides that are Almost A+ graded, I am a very friendly person: If you would not agreed with my solutions I am ready for refund

4.6

237 reviews

5
192
4
14
3
15
2
5
1
11

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions