What provision in Planning can be made for implementing Requests for Change?
A. Project and stage tolerances
B. Contingency plans
C. A Change Budget
D. Adding a contingency margin to estimates
D
A project is a management environment that is created for the purpose of
delivering one or more business products
according to ........... ?
A. TheCustomer'sNeds
B. An Agreed Contract
C. The Project Plan
D. A specified Business Case
B
In what sequence would the
(a) Project Initiation Document,
(b) the Project Mandate and
, 2
(c) the Project Brief appear in a PRINCE2® project?
A. a, b, c
B. b, c, a
C. c, a, b
D. c, b, a
D
Which would require the production of an Exception Report?
A. When a Project Issue is received
B. When a Project Board member raises a complaint
C. When a Request For Change or Off-Specification has been received
D. When the current forecasts for the end of the stage deviate beyond the delegated
tolerance bounds
C
Which statement is NOT a fundamental principle of" Closing a Project"? "A clear
end to a project"
A. provides a useful opportunity to take stock of achievements
B. provides an opportunity to ensure that all unachieved goals and objectives are
identified
C. provides the opportunity to evaluate achievement of all the expected benefits
D. is always more successful than the natural tendency to drift into operational
Management
C
What is the more common term used in PRINCE2® for
"deliverable"?
A. Item
B. Package
C. Product
, 3
D. Component
D
Which of these items does NOT involve the Project Board?
A. Exception Assessment
B. Highlight Reports
C. Project Closure
D. Work Package Authorisation
D
What name is given to the permissible deviation from a plan allowed without
immediate reporting to the Project Board?
A. Allowance
B. Contingency
C. Concession
D. Tolerance
C
What other control is closely linked with configuration management?
A. Risk Management
B. Project Closure
C. Change Control
D. Project Initiation
D
Which of these processes does NOT trigger the Planning (PL) process?
A. Starting Up a Project (SU)
B. Initiating a Project (IP)
C. Managing Stage Boundaries (SB)
D. Controlling a Stage (CS)
CISI SAMPLE PAPER 1 EXAM LATEST UPDATES -
2025/2026- ACTUAL QUESTIONS AND CORRECT
ANSWERS ALREADY GRADED A+ GUARANTEED
SUCCESS
What provision in Planning can be made for implementing Requests for Change?
A. Project and stage tolerances
B. Contingency plans
C. A Change Budget
D. Adding a contingency margin to estimates
D
A project is a management environment that is created for the purpose of
delivering one or more business products
according to ........... ?
A. TheCustomer'sNeds
B. An Agreed Contract
C. The Project Plan
D. A specified Business Case
B
In what sequence would the
(a) Project Initiation Document,
(b) the Project Mandate and
, 2
(c) the Project Brief appear in a PRINCE2® project?
A. a, b, c
B. b, c, a
C. c, a, b
D. c, b, a
D
Which would require the production of an Exception Report?
A. When a Project Issue is received
B. When a Project Board member raises a complaint
C. When a Request For Change or Off-Specification has been received
D. When the current forecasts for the end of the stage deviate beyond the delegated
tolerance bounds
C
Which statement is NOT a fundamental principle of" Closing a Project"? "A clear
end to a project"
A. provides a useful opportunity to take stock of achievements
B. provides an opportunity to ensure that all unachieved goals and objectives are
identified
C. provides the opportunity to evaluate achievement of all the expected benefits
D. is always more successful than the natural tendency to drift into operational
Management
C
What is the more common term used in PRINCE2® for
"deliverable"?
A. Item
B. Package
C. Product
, 3
D. Component
D
Which of these items does NOT involve the Project Board?
A. Exception Assessment
B. Highlight Reports
C. Project Closure
D. Work Package Authorisation
D
What name is given to the permissible deviation from a plan allowed without
immediate reporting to the Project Board?
A. Allowance
B. Contingency
C. Concession
D. Tolerance
C
What other control is closely linked with configuration management?
A. Risk Management
B. Project Closure
C. Change Control
D. Project Initiation
D
Which of these processes does NOT trigger the Planning (PL) process?
A. Starting Up a Project (SU)
B. Initiating a Project (IP)
C. Managing Stage Boundaries (SB)
D. Controlling a Stage (CS)