1. What material is the proper material for tubing in a Category 1 oxygen
system? - ANSWER ASTM B819 hard drawn seamless medical gas
copper tubing.
2. What is the chronological order for a hospital construction project in terms
of programs, development and construction? - ANSWER 1. Functional
Program, Architectural Program, Design Development, Construction
Drawings.
3. Vibration is extremely important to mitigate in what Area?
1. NICU
2. Surgery
3. AII
4. PACU - ANSWER NICU
4. For CHC purposes what 3 items are Captial costs - ANSWER Major
construction
Major renovation
Major Equipment
,5. A reason for having all normal (non-emergency) branch circuits fed from a
single distribution panel at a particular patient bed location is to minimize -
ANSWER Possible potential differences between outlet grounds.
6. What are the only two types of medical gas system REQUIRED in a typical
medical/surgical patient room - ANSWER Vacuum and Oxygen
7. What treatment areas require lead as a shielding material? - ANSWER
CT Room
8. Which department of an acute care hospital must be staffed 24 hours a day,
7 days of a week. - ANSWER Emergency
9. Before an employee enters a permit-required confined space, the internal
atmosphere shall be tested with a calibrated direct reading instrument for
oxygen content and which of the following - ANSWER Potential toxic air
contaminants, and flammable gasses and vapors
10.Medical devices that are typically more common in neonatal intensive care
units than in adult intensive care units include which of the following:
1. Ventilator
2. Infusion Pumps
3. Physiological Monitor
4. Incubator - ANSWER Incubator
11.What pressure should Oncology have in regards to positive and negative -
ANSWER It should be Positive
,12.What separation is required when two buildings are connected that have
separate CMS providers or separate independent utilities - ANSWER 2
hours
13.What technique does the CDC recommend for evaluating the integrity of
temporary construction barriers - ANSWER airborne particle counting
of occupied areas
14.What is a tool that is used by a hospital in developing an emergency
management plan? - ANSWER Hazard Vulnerability Analysis (HVA)
15.Which of the following conditions would most likely compromise the
integrity of a smoke barrier?
1. Non functional smoke dampers
2. Non-functional door latching hardware
3. Drywall construction that has water damage
4. oversized kick plates on cross corridor doors - ANSWER Non functional
smoke dampers
16.Which entity requires healthcare institution to establish an emergency
communications plan? - ANSWER The Joint Commission
17.The decline in exploratory surgery in recent years in primarily due to? -
ANSWER Improved medical imaging capabilities
, 18.According to the Bureau of of Labor Stats, what is the MOST common cause
of construction worker injury and death on a healthcare construction
project - ANSWER Fall from heights
19.What should you do if you break a sprinkler head in a patient care area of a
hospital? - ANSWER Notify the hospital facilities personnel
Assist in the shutdown
Clean up as directed by the project super
20.What financial tool could be the quickest way to determine the financial
viability of an energy saving measure? - ANSWER Simple Payback
21.What are the 3 things critical to the site logistics plan? - ANSWER
Emergency Vehicle Access, construction lay down areas, and patient visitor
areas
22.NFPA 241-2009 Standard for Safeguarding Construction, Alteration, and
Demolition Operations requires that construction areas be separated from
occupied areas within a non sprinklered building by a minimum fire rated
barrier of - ANSWER 1 hour
23.What function of the HVAC system is unique to healthcare? - ANSWER
Infection Control