Where are leak tests B345
found
prior to initial operation
after completion of applicable examinations in 341
required
When is leak test
after heat treatment
performed
leave all joints exposed (no insulation)
may be primed and painted Except sensitive leak test
cat D fluid may be insulated at owners option
t=PD/2(SEW+PY)
P=Gage pressure
D=Outer diameter, actual
straight pipe under S=Stress value. Table A-1
internal pressure t formula E=Quality factor Table A-1A 1.0 for most sml pipe
W=Weld joint reduction factor W. table 302.5. Kicks in
at 850F
Y=coefficent Table 304.1.1 0.4 typical