Which of the following is a direct responsibility of the project manager?
A. drawing the network diagram
B. performing all of the activities in the project
C. making sure that the people assigned to the project receive the motivation, direction, and
information needed to do their jobs
D. calculating completion probabilities for all tasks in the project - ANSWER-C. making sure that
the people assigned to the project receive the motivation, direction, and information needed to
do their jobs
The Frito-Lay plant applies a product focus strategy, which is appropriate for what type of
producer?
A. high-volume, low-variety
B. low-volume, high-variety
C. low-volume, low-variety
D. high-volume, high-variety - ANSWER-A. high-volume, low-variety
1|Page
, OM 300 EXAM 1 NEWEST 2025
A set of skills, talents, and capabilities in which a firm is particularly strong is referred to as
A. experience differentiation.
B. core competencies.
C. differentiation.
D. key success factors (KSFs). - ANSWER-B. Core competencies
Gantt charts are
A. not widely used.
B. widely used network techniques.
C. not easy to understand.
D. planning charts used to schedule resources and allocate time. - ANSWER-D. planning charts
used to schedule resources and allocate time
The critical path of a network is the
A. shortest time path through the network.
2|Page
, OM 300 EXAM 1 NEWEST 2025
B. longest time path through the network.
C. path with the fewest activities.
D. path with the most activities. - ANSWER-B. longest time path through the network
How is the EF computed?
A. ES + Activity time
B. LF − Activity time
C. Max{EF of all immediate predecessors}
D. Min{LS of all immediate following activities} - ANSWER-A. ES + Activity time
With respect to PERT and CPM, slack
A. is a task or subproject that must be completed.
B. marks the start or completion of a task.
C. is the amount of time a task may be delayed without changing the overall project completion
time.