Terms in this set (117)
With whom should the C. The structural engineer
interior designer consult
to determine where to
locate the standing
stacks in a library?
A. mech engineer
B. library planner
C. structural engineer
D. fire protection designer
In specifying new window A. Verify the building owner approves of the
coverings and change in the building's exterior appearance
tracks to replace building
standard window C. Determine if the mech. engineer objects to the
coverings, what replacement plans
coordination is MOST
important for the ID to E. Verifying with the manuf. that flammability does not
pose a problem
undertake? (choose 4
that apply)
F. checking with the architect that the new
coverings do not adversely effect the heating
A. Verify the building
of the glass
owner approves of the
change in the
building's exterior
appearance
B. Asking the
1/
21
,6/22/25, 1:36
PM
electrical engineer if
the new light
reflectance is
detrimental
C. Determine if the
mech. engineer objects
to the replacement
plans
D. getting approval from
the client
concerning the color of
the coverings
E. verifying with the manuf.
that
flammability does not
pose a problem
F. checking with the
architect that the new
coverings do not
adversely effect the
heating of the glass
In designing a new space, Sprinklers
the ID can
influence life safety MOST
by coordinating with the
consultant concerning
what?
Who is responsible for Electrical Engineer
showing the
telephone and data
conduit runs on the
drawings for a
commercial design
project?
Who would be Woodwork fabricator
responsible for
ordering and placing a
stone top of a custom
built reception desk
2/
21
, 6/22/25, 1:36
PM
that includes
woodwork, stone,
metal and a light
fixture?
Who is responsible for The interior designer
verifying that a
recessed downlight does
not interfere with the
ductwork shown on
the mechanical
plans?
The final responsibility owner
of awarding a contract
rests with the..
An interior designer Dealership.
has written furniture
specs for a project and
has put the job out for
bid to several
dealerships. In this
situation, purchase
orders are MOST likely
to be written by
the...
Who is responsible for The Interior Designer.
determining the
location and general
conditions of existing
light fixtures as part of
a due diligence
investigation?
Which type of chart is CPM chart
MOST often used with
complex projects to
3/
21