Answers (100% Correct Answers) Already Graded
A+
Quiz: - LEED Process -
Having the right structures for internal and external personnel to make sure
the project team is keeping on top of tracking is important for:
a) owner's project requirements
b) recertification
c) meeting minimum program requirements
d) current facilities requirements, Ans: Recertification
Continuous tracking is critical to the success of recertification
Quiz: - LEED Process -
What detail in a tracking system are important for recertificaiton?
a) number of desk
b) newer versions of LEED
c) number of FTEs
d) minimum occupancy reqs., Ans: number of FTEs
© 2025 Get it right Stuvia US All rights reserved
,These are additional inputs to ENERGY STAR that need to be tracked over time
in case the values shift. The quantities and dates of any changes need to be
documented to get accurate results
Quiz: - LEED Process -
A project team for a school is preparing for recertification. During the
performance period no major changes have occurred. What will the project
team need to submit for review?
a) site management policies
b) site infrastructure information
c) purchasing policies
d) only performance documentation, Ans: only performance documentation
unless major changes have occur (as defined by renovation, addition or
management turnover) only performance docs. needs to be submitted for
recertification
Quiz: - LEED Process -
What is the max gap a project can have in between performance periods?
a) none
b) 1 full week
c) 3 months
d) 8 months, Ans: 1 full week
© 2025 Get it right Stuvia US All rights reserved
,Quiz: - LEED Process -
Unless otherwise noted in the credit requirements how long is the initial
performance period?
a) at least 12 months but no longer than 5 yrs
b) at least 3 mo. but no more than 24 months
c) at least 12 months
d) at least 8 months but no longer than 36 months, Ans: At least 3 months but
no more than 24 months
Quiz: - LEED Process -
All performance periods must overlap and conclude within how may days of
each other?
a) 7 days
b) 30 days
c) 10 days
d) 3 months, Ans: 30 days
Quiz: - LEED Process -
A project has the following credits and end dates for their performance
periods:
WE Credit Outdoor Water Use April 1, 2015
SS Credit Site Management April 25, 2015
EA Prerequisite Minimum Energy Performance April 26, 2015
© 2025 Get it right Stuvia US All rights reserved
, What is the latest date the project team can submit the project application?
a) In 60 days, counting from April 27
b) In 60 days, counting from April 26
c) In 60 days, counting from April 1
d) In 30 days, counting from April 26, Ans: A) in 60 days, counting from April 27
-60 days after starting on the day after the last day of the performance period
Quiz: - LEED Process -
How often are projects eligible to be re-certified?
a) every 3 months
b) every 12 months
c) every 5 yrs
d) every 24 months, Ans: B) every 12 months
projects must re-certify within five years of the previous certification and are
eligible to recertify every 12 months
Quiz: - LEED Process -
A team is gathering to discuss the project goals. What should the project goals
reflect?
a) the values of the org. that owns the building
b) operations realities
© 2025 Get it right Stuvia US All rights reserved