1. Operational Planning Analysis is a Reliability Analysis studies conducted by
Reliability Coordinators for the purpose to assess whether the planned
operations for the next day within its Wide Area, will exceed
A) any of its Interconnection Reliability Operating Limits
B) Cost/profitability of maintaining economic dispatch
C) Operating limitations of generating facilities
D) Available Transfer Capability - ANSWER ✓ A) any of its
Interconnection Reliability Operating Limits
2. The ________________ must have the authority, plan, and agreements in
place to immediately direct reliability entities within their
_________________ Areas to re-dispatch generation, reconfigure
transmission or reduce load to mitigate critical conditions and return the
system to a reliable state.
A) Reliability Coordinator; Reliability Coordinator
B) Balancing Authority; Balancing
C) Transmission Operator; Transmission
D) Operations; Planning - ANSWER ✓ A) Reliability Coordinator;
Reliability Coordinator
,3. When a Reliability Coordinator is performing the next-day analysis for its
Reliability Coordination Area, what information is required for the system
study?
A) Area Interchange Error (AIE) documents, area inadvertent
accumulations, weather forecast and geomagnetic forecasts.
B) Interchange transactions, area inadvertent accumulations, staffing
summaries, and load.
C) Critical facility status, load, generation, operation reserve projections,
and known interchange transactions.
D) Load, generation, Area Interchange Error (AIE) documents,
operations reserve projections, and staffing summaries. - ANSWER ✓
C) Critical facility status, load, generation, operation reserve
projections, and known interchange transactions.
4. A Balancing Authority was only 95% compliant with the DCS criteria for
the first quarter of the year. What action must the Balancing Authority take?
A) Must carry additional regulating reserve for 3 months starting April 1.
B) Must carry additional regulating reserve for 3 months starting May 1.
C) Must carry additional contingency reserve for 3 months starting May
1.
D) Must carry additional contingency reserve for 3 months starting April
1. - ANSWER ✓ C) Must carry additional contingency reserve for 3
months starting May 1.
5. Sufficient Operating Reserve is defined as the capacity required to meet
what?
A) DOE specifications
B) CPS and DCS
, C) Capacity Standard
D) CPS 1 & 2 only - ANSWER ✓ B) CPS and DCS
6. If a Balancing Authority has an ACE of -175 MW and Frequency is 59.85
Hz. Which real-time Control Performance Standard maybe outside of its low
limit?
A) AGC
B) BAAL
C) DCS
D) CPS1 - ANSWER ✓ B) BAAL
7. EMS and AGC have failed at 12:25 and generation must be controlled
manually. At the top of the hour, load is expected to increase 100 MWs,
imports will increase by 75 MWs. ACE is reading 25 MWs. What should the
operator do now after verifying the ACE value?
A) Increase generation by 25 MWs for the top of the hour
B) Increase generation by 50 MWs
C) Decrease generation by 25 MWs
D) Decrease generation by 50 MWs - ANSWER ✓ C) Decrease
generation by 25 MWs
8. Which of the following conditions describes a case where a Balancing
Authority is hindering the Interconnection scheduled frequency?
A) ACE is negative while frequency is below 60.00 Hz
B) ACE is positive while frequency is 60.00 Hz
C) ACE is negative while frequency is above 60.00 Hz
, D) ACE is positive while frequency is below 60.00 Hz - ANSWER ✓ A)
ACE is negative while frequency is below 60.00 Hz
9. Balancing Authority "A" is importing 225 MWs,and is only scheduled to
import 200 MWs. The BAs Beta is 200 MWs/.1 Hz and frequency is 59.99
Hz. What does ACE indicate?
A) 45 MW over-generating
B) 45 MW under-generating
C) 20 MW over-generating
D) 20 MW under-generating - ANSWER ✓ B) 45 MW under-generating
10.A Balancing Authority has a normal load of around 8500 MW. Its most
severe single contingency is a 700-MW coal-fired steam unit. At 0810 the
ACE value was at -55 MW when a 600-MW generator in the Balancing
Authority's northern area tripped off line as the result of a generator
differential. This resulted in a large negative ACE for the Balancing
Authority. What value must the ACE return to and in what time frame to
avoid a DCS violation?
A) -55 MW ACE in 10 minutes
B) Zero ACE in 15 minutes
C) -55 MW ACE in 15 minutes
D) This did not constitute a reportable disturbance. - ANSWER ✓ C) -55
MW ACE in 15 minutes
11.A Balancing Authority is performing Overlap Regulation Service for another
Balancing Authority. Which of the following statements applies to the
Balancing Authority providing this service?
A) The Balancing Authority shall use the larger of the two Frequency