Started Monday, 17 March 2025, 10:14 PM
Completed Monday, 17 March 2025, 10:33 PM
Duration 19 mins 35 secs
Grade 10.0 out of 10.0 (100%)
Question 1
Correct
Mark 2.0 out of 2.0
From the four answers provided below, please select the MOST CORRECT option that best aligns to the query posed in Question 1 within the
Topic 4 lecture. Please remember that the terms have been replace with 'X' and 'Y'. Therefore, ensure that you have the meanings of the 'X'
and 'Y' codes before you start this question. Hint: Read the options carefully, as there is only one fully correct option.
Select one:
1. 'Xs' must have predecessors and successors, but must not be aligned through leads or lags. Alternately, 'Ys' must always have leads
and lags, as well as having a clear duration and resource requirements.
2. 'Xs' refer to significant events that normally have no duration, cost or resource requirements associated with them. 'Ys' are elements
of work normally found in a WBS, which have an expected duration, cost and resource requirements.
3. 'Xs' by definition have no duration, but must have a logical relationship with 'Ys'. These relationships may include the provision of
leads and lags. Alternately, 'Ys' must have a duration and resource allocations, so they can be applied to coordinate the Xs.
4. 'Xs' are elements of work normally found in a WBS, which have an expected duration, cost and resource requirements. 'Ys' refer
to significant events that normally have no duration, cost or resource requirements associated with them.
Question 2
Correct
Mark 2.0 out of 2.0
Insert the correct words into the paragraphs shown below, so you can answer Question 2 within the Topic 4 lecture. Hint: Please read the
options carefully as not all of the words that are available in the options are appropriate.
The following principles should be applied:
Specific , means that the title of the milestone should be clear and provide a concise understanding of what it is defining.
Measurable , defines the intent that the milestone must provide a concise indication, which will help to illustrate the degree to
which the project is progressing, by showing what has actually been achieved by that point in time.
Achievable , refers to the fact that the milestone must be realistic, practical, and attainable.
Relevant , means that the milestone must be linked directly to priorities that are designed to deliver the required outcome.
Time-Bound , is a critical aspect of all milestones, because they must provide clear deadlines.