1. Takeoffs of conduit are categorized into ______. - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Power distribution, branch lighting, and branch
|\ |\ |\ |\ |\ |\ |\
power
2. Raceways are taken off per _____. Fittings required to make
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
turns and extensions are taking off per _____. - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Linear foot, each |\ |\ |\
3. All wires and conductors are taken off per _____. - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Linear foot |\ |\
4. All fittings, devices and boxes are taken off per _____. -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔Each Item |\ |\ |\
5. Permits and fees for tie-ins may be listed at lump sum and are
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
taken off per _____. - CORRECT ANSWERS ✔✔Occurrence,Project,
|\ |\ |\ |\ |\ |\ |\ |\
and Contract
|\
6. Control stations are taken off by _______. - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔Individual Unit and Each Item. |\ |\ |\ |\
7. Panelboards are taken off individually according to ______. -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔Type, Size, and Voltage
|\ |\ |\ |\ |\
,8. Starters, safety switches and fuses are taken off per _______. -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔Each Item |\ |\ |\
9. _______ should be kept separate from general light fixtures. -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔Exit Lighting |\ |\ |\
10. Interior and exterior lighting should be taken off and listed
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
_______. - CORRECT ANSWERS ✔✔Separately
|\ |\ |\ |\
11. Lamps for light fixtures are _______. - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔Taken off per each Item |\ |\ |\ |\
12. Light fixtures should be listed in the takeoff according to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
_______. - CORRECT ANSWERS ✔✔Color
|\ |\ |\ |\
13. Working electrical drawings numbered sequentially, prefaced
|\ |\ |\ |\ |\ |\ |\
by the letter "E", include _______. - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔Telecommunications and security systems only |\ |\ |\ |\
14. The _______ shows power requirements of the structure. -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔Power plan |\ |\ |\
15. The _______ aids the electrical contractor sizing the panel. -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔Panel Schedule|\ |\ |\
, 16. The _______ plan is supplemented by the fixture schedule. -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔Lighting |\ |\
17. The fixture schedule lists lamp _______. - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔Wattage
18. Electrical specifications provide _______. - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\
✔✔The grade of materials to be used, Materials installation
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
specifics, and how materials will be used in the finished system
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
19. _______ must be maintained by the electrical contractor for all
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
installed work. - CORRECT ANSWERS ✔✔As-built drawings
|\ |\ |\ |\ |\ |\ |\
20. No conductors are smaller than No. _______ wire. - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔12 |\
21. _______ Shall be installed in service entrances and panel
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
feeders. - CORRECT ANSWERS ✔✔Rigid conduit
|\ |\ |\ |\ |\
22. The electrical contractor is responsible for providing and
|\ |\ |\ |\ |\ |\ |\ |\ |\
installing _______ for a complete telephone system. - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Outlet boxes, pull boxes, and empty raceways
|\ |\ |\ |\ |\ |\ |\
23. Interpretation of construction drawings and specifications
|\ |\ |\ |\ |\ |\ |\
may conflict when _______. - CORRECT ANSWERS ✔✔Standard
|\ |\ |\ |\ |\ |\ |\ |\
specifications are used with specific working plans, previously
|\ |\ |\ |\ |\ |\ |\ |\
prepared plans are changed and referenced in the specifications
|\ |\ |\ |\ |\ |\ |\ |\ |\