What procedure is used to GSP 10
sample bituminous
materials?
What procedure is used to GSP 15
sample hot mix asphalt
mixtures from full trucks,
roadways, or occasionally
partially loaded trucks?
How do you take a HMA Shovel off about 60% of the cone and go atleast 6
sample from a truck? inches deep.
What kind of shovel do A square nosed shovel.
you use to take a sample
off of a truck?
What procedure governs GSP 21
the sampling procedures
for contractor acceptance
testing of HMA?
When should the QC take Every time a sample is take. +\- 20f or +\- 11c
the temperature of the mix
and what is the tolerance?