Question:When a repair must be performed in a emergency situation, when shall the permit application be submitted? Ans: The next working business day Section 105.2.1 Emergency Repairs Question: Once the permit has been issued, how long is it valid? Ans: 180 days Section 105.5- Expiration Question: How long should a permit remain at the site of the work? Ans: Until the completion of the project Section 105.7 Placement of permit Question: What included within the "Exterior wall envelope"? Ans: flashing intersections with dissimilar materials, corners, end details, control joints, intersections at roofs, eaves or parapets, means of drainage, water-resistive membranes and details around openings. Question: Built-Up roof covering consist of Ans: Two or more layers of felt cemented together and surfaced with a cap sheet, mineral aggregate, smooth coating or similar surfacing material Chapter 2- Definition-Built-up Roof covering

Meer zien Lees minder
Instelling
General Contractor License
Vak
General Contractor License

Voorbeeld van de inhoud

Page | 1



General Contractor License Questions
with Detailed Verified Answers

Question:When a repair must be performed in a emergency situation, when
shall the permit application be submitted?

Ans: The next working business day

Section 105.2.1 Emergency Repairs

Question: Once the permit has been issued, how long is it valid?

Ans: 180 days

Section 105.5- Expiration

Question: How long should a permit remain at the site of the work?

Ans: Until the completion of the project

Section 105.7 Placement of permit

Question: What included within the "Exterior wall envelope"?

Ans: flashing intersections with dissimilar materials, corners, end details,
control joints, intersections at roofs, eaves or parapets, means of drainage,
water-resistive membranes and details around openings.

Question: Built-Up roof covering consist of

Ans: Two or more layers of felt cemented together and surfaced with a cap
sheet, mineral aggregate, smooth coating or similar surfacing material

Chapter 2- Definition-Built-up Roof covering

, Page | 2

Question: Positive roof drainage will ensure drainage of the roof within ___
hours of precipitation

Ans: 48 hours

Chapter 2 Positive roof drainage

Question: An example of a live load on a roof includes?

Ans: During maintenance by workers, during the life of the structure by
movable objects, and by the use and occupancy of the roof for roof gardens or
assembly areas



Chap 2 Live loads, ROOF

Question: A _____ is the process of installing an additional roof covering over
a prepared existing roof covering without removing the existing roof.

Ans: Roof Recover

Chap 2 Definitions roof recover

Question: Parapet walls shall be not less than _____ inches above the point
where the roof surface and the wall intersect

Ans: 30 inches

Section 705.11.1 Parapet Construction

Question: What is the requirement for combustible roof insulation?

Ans: It must be covered by an approved roof covering

Section 720.5 roof insulation

Question: An opening not less than 20"x30" shall be provided to any attic area
having a clear height of over_____

, Page | 3

Ans: 30 inches

Section 1208.2 Access to Unoccupied Spaces- Attics Spaces

Question: Flashing shall be installed at the perimeters of exterior door and
window assemblies, penetrations and terminations of exterior wall
assemblies, and what other locations?

Ans: Exterior wall intersections with roofs, chimneys, porches, decks,
balconies and similar projections and at built-in gutters and similar locations
where moisture could enter the wall

Section 1404.4 Installation of wall covering flashing

Question: When a scupper is used as secondary roof drainage, what is the
minimum opening size of the scupper?

Ans: 4 inches

Section 1502.3 Scuppers

Question: A cricket shall be installed where a roof penetration is greater than
___ inches wide when measured perpendicular to the slope?

Ans: 30 inches

Section 1503.5 Cricket and Saddles

Question: A building with aggregate roofing in an area with a nominal design
wind speed of 110 mph in exposure category C can have a maximum roof
height of how many feet

Ans: No permitted

Table 1504.8 Table for Maximum allowed mean roof height permitted for
buildings aggregate on the roof outside an HVHZ

Question: How many layers of underlayment are required for an asphalt
shingle roof with a slope of 2:12?

, Page | 4

Ans: 2 layers

Section 1507.2.2- Asphalt Shingles Slope

Question: How far into asphalt shingle roofing materials shall fasteners
penetrate into the roof sheathing?

Ans: Minimum of 3/4"

Section 1507.2.5 Fasteners

Question: An ice barrier shall extend from the lowest edge of the roof surface
a point at least ___ inside the exterior wall line of the building

Ans: 24 inches

Section 1507.2.1 Ice barrier

Question: What is the minimum thickness, in inches, of cap flashing for a
roof?

Ans: .019 inches

Section 1507.2.8.1 Base and cap flashing

Question: For a tile roof with a slope of 5 in 12, what is the minimum number
of layers of underlayment and lap?

Ans: 1 layer lapped 2 inches

Table 1507.1.1(2) - Clay and concrete tile

Question: Valley flashing shall extend at least ____ from the centerline of the
valley each way.

Ans: 11 inches

Section 1507.3.9 - Flashing

Geschreven voor

Instelling
General Contractor License
Vak
General Contractor License

Documentinformatie

Geüpload op
17 juli 2025
Aantal pagina's
55
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$14.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Ivie Stuvia
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
31
Lid sinds
1 jaar
Aantal volgers
1
Documenten
8539
Laatst verkocht
1 maand geleden

3.4

7 beoordelingen

5
2
4
2
3
1
2
1
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen