Which four items are required parts of the Transmittal Memorandum? - ANSWER-
Applicable explosives safety references
Site location
Requested approve by date
Point of contact (POC) for the ESSP
Which three mistakes commonly occur when submitting an ESSP? - ANSWER-
submitting a map without an indication of true north
Leaving out the lightning protection system (LPS) drawings
Sending a map with no scale indicated
The purpose of an ESSP is to ensure safety, provide specifications, and - ANSWER-
establish limits
ILD is the minimum distance permitted between - ANSWER-two operating
buildings
1|Page
, ARMY EXPLOSIVES SAFETY SITE PLANNING CERTIFICATION EXAM
Your installations is refurbishing an existing PES facility. Do you need to complete
an ESSP? - ANSWER-Yes, and it requires DDESB approval.
You must submit an ESSP for DDESB approval if the installation is - ANSWER-
Building an ES within an existing ESQD arc
Who must accept identified risks? - ANSWER-Installation Commander
Failing to submit a successful ESSP can result in impaired operational capability,
decreased production, and - ANSWER-delay in construction
Which part of the ESSP package contains background information, site location,
and the reason for ESSP submission? - ANSWER-ESSP narrative
All of these are requirements of an ESSP except? - ANSWER-Tenant unit approval
Which of these requirement must appear on a site map? - ANSWER-Scale 1 in
=400 ft
What part of an ESSP package contains blast hazards, fragment hazards, and the
glass hazard risk assessment? - ANSWER-Evaluations
You must submit the ESSP package - ANSWER-Electronically through secure
command channels.