Which three items are included in the Evaluations section
of an ESSP package? - ANSWER-Electrical installation
Lightning protection information
Glass hazard risk assessment
What part of the ESSP package contains background
information, site location, and reason for the ESSP? -
ANSWER-ESSP narrative
Who has ultimate approval authority for an ESSP? -
ANSWER-DoD explosives Safety Board (DDESB)
,2|Page
The purpose of an Expedited Approval Request is to -
ANSWER-Justify why an expedited approval is required
Which four items are required on installation maps? -
ANSWER-Installation boundaries
Roads and railways
Waterways and ponds
Facilities and associated utilities
Which of these is a site map requirement? - ANSWER-
Scale 1 in = 400 ft
Which four items are required parts of the Transmittal
Memorandum? - ANSWER-Applicable explosives safety
references
, 3|Page
Site location
Requested approve by date
Point of contact (POC) for the ESSP
Which three mistakes commonly occur when submitting
an ESSP? - ANSWER-submitting a map without an
indication of true north
Leaving out the lightning protection system (LPS)
drawings
Sending a map with no scale indicated