The performance of tasks, which ensure that
Construction quality construction is performed according to plans and
management specifications, on time, within a defined budget, and a
safe work environment.
Quality Conformance to properly developed requirements
The government's efforts, separate from, but in
coordination and cooperation with the contractor,
Purpose of CQM
assure that the quality set by the plans and
specifications is achieved.
Contractor quality control To assure that the completed project meets all quality
function requirements of the contract.
Increased profit and production, better
Contractor benefits of communications, planning, improved organizational
CQM skills, and outstanding performance evaluations to
obtain future contracts.
Two factors cause Changing market and increased tech and regulations
construction industry to
become highly
specialized
https://quizlet.com/1062684319/cqm-for-usace-2025-exam-questions-frequently-tested-questions-verified-solutions-100-correct-flash-cards/?new 1/8
, 7/28/25, 7:08 PM CQM for USACE 2025 EXAM QUESTIONS |FREQUENTLY TESTED QUESTIONS ||VERIFIED SOLUTIONS (100% CORRECT) Fl…
New govt regulations, greater influence from
customer, improvement of QC and QA requirements,
Factors that will influence
construction-oriented mgmt info systems, formal
both the govt and
partnering involving stakeholders, more reliance on
construction industry in
design-build, more consideration for life cycle
the future
requirements, increased performance based
incentives
Pre construction Required prior to or at start of construction or the
submittals next major phase on a multi phase contract
Scheduled and a tabular list of locations, features, and
Preconstruction submittals other pertinent information regarding products,
include: materials, equipment, or components to be used in
work
Catalog cuts, illustrations, schedules, diagrams,
Product data performance charts, instructions, systems and
equipment
Fabricated or I fabricated physical examples of
materials, equipment, or workmanship that illustrate
Samples
functional and aesthetic characteristics of material or
product that establish standards
Calculations, mix designs, analyses pertaining to a
Design data
part of work
Signed by authorized official of laboratory that a
material, product or system to be provided has been
Test reports tested in accord with specified requirements, unless
otherwise specified, must have been done within 3
years of date of contract award
Statements printed on the manufacturer's letterhead
and signed by responsible officials of manufacturer's
Certificates product, system, or material meets spec requirements.
Must be dated after award of project contract and
clearly name the project