Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

DBIA EXAM NEWEST VERSION ACCURATE ACTUAL EXAM COMPLETE QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+ | WITH A STUDY GUIDE

Beoordeling
-
Verkocht
-
Pagina's
44
Cijfer
A+
Geüpload op
05-08-2025
Geschreven in
2025/2026

DBIA EXAM NEWEST VERSION ACCURATE ACTUAL EXAM COMPLETE QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+ | WITH A STUDY GUIDE Project Delivery System - ANSWER How team members are organized, establishes when parties engage, determines roles of parties, and determines sequence of design, procurement, and construction (db, cmar, dbb) Procurement Method - ANSWER how team members are selected (QBS, best value, low price, sole source) contracting approach - ANSWER how team members are paid (fp, gmp, cost reimbursement, target price, unit price) Design-Bid-Build (DBB) - ANSWER linear, sequential process, A/E selected on qualifications, GC selected on low price, design is fully completed without input from GC, A/E acting in owner's interests, with a historically strong bond, process is well-established and understood construction manager at risk - ANSWER similar org structure to DBB, construction manager selected by QBS or best value, contractor provides precon services, negotiated gmp contracting approach, open book estimating process, potential to fast track project, construction cost determined before design completed, potential issues over what is reasonably inferable from gmp design documents Design-Build - ANSWER The owner contracts with one entity (a person or firm) to provide both design and construction services, designer and contractor have a direct contractual relationship, selected by QBS or best value, wide spectrum of contracting approaches and organizational structures, single point responsibility, owner does not manage designer, owner exposure to claims is significantly reduced engineer procure construct (epc) - ANSWER similar to design build, in industrial and power generation sectors, systems and performance testing are central to scope, contractor will typically perform engineering with its in-house staff, owner has need for single point responsibility, contracts include plant and process performance guarantees, contract items include performance and schedule liquidated damages and limitations of liability Multiple Prime Contracting - ANSWER owner contracts with multiple trade contractors, attributes are typically similar to dbb, owner's ability to schedule and coordinate the work Integrated Project Delivery (IPD) - ANSWER multi-party agreement - all parties equal, QBS procurement and target pricing contract approach, private sector use (limited at this time), key: owner's ability to accept risk Lowest Price Technically Acceptable (LPTA) - ANSWER contract requirements are clearly definable and minimal risk of unsuccessful contract performance; suitable for commodities or simple service; proposers do the minimum for the pass/fail process; impedes thinking creatively or creating the best team; little practical ability for an owner to ever fail someone Sole source - ANSWER Only one vendor can provide what your project needs to purchase. Examples include a specific consultant, specialized service, or unique type of material. essentially non-competitive; multiple contracting approaches available (unit rates, cost plus, GMP, or lump sum) RFQ - ANSWER goal: to get highly qualified teams and information that will serve to differentiate among proposers and evaluate past performance RFP - ANSWER communicates needs for firm pricing; perform front-end tasks (like geotech) for baselines; only asks for relevant and reasonably needed information; allows ATCs when mandatory technical criteria is established public-private partnership (p3) - ANSWER Instead of government building and maintaining major infrastructure (such as highway, water treatment plant), build and maintenance is outsourced to a private company. Opposed by public sector unions. this is not considered a delivery system but its underlying approaches are delivery systems and typically use DB. multiple procurement and contracting approaches shift left - ANSWER intense efforts to establish scope early in the process; drives early team formation to include key trade subcontractors; can enable big decisions to be made early, affect project outcomes at lowest cost, establish a need for co-location and collaboration, and compress time during concurrent design and construction traditional design build - ANSWER typically two-phase best value procurement with lump sum contract; owner defines project requirements and scope of prescriptive work; use of performance-based technical requirements with limited prescriptive specifications progressive design build - ANSWER design and price are progressively developed after the design-builder is under contract; final project cost and schedule commitment is not established as part of the selection process; two phases: preliminary services and final design and construction services criteria documents - ANSWER describe the end result bridging documents - ANSWER prescribes how to achieve the end result design bid build paradigm - ANSWER prior to bidding, owner undertakes a process to design the project and all of its details to 100% complete plans and specs. the owner is therefore responsible for success or failure of details of the design, and warrants the sufficiency of design to the contractor. the owner is therefore liable to the contractor for any gaps between plans and specifications and owner's requirements for project performance design details responsibility - ANSWER the owner should define its performance requirements and award the contract on the basis of preliminary design; this makes the design-builder responsible for completing the design in accordance with the owner's performance requirements. that also causes the design-builder to warrant the sufficiency of the design to meet the owner's criteria and the sufficiency of the design to subcontractors/suppliers that have no design responsibility uniformat - ANSWER subdivides project by functional elements, focuses on systems and assemblies, useful for preliminary information and early design phases, aligns with BIM models and conceptual estimating masterformat - ANSWER subdivides work by results/trades, focuses on building materials, products, and activities, useful for detailed information during final design and construction phases, and aligns with detailed estimating functional requirement - ANSWER a specific business need or behavior as seen by an external user of the system; describe what functions/operations the end product must perform/accommodate; examples: regulatory, permitting, economic, and others that define functions and operational capability. "Build an office building on my existing lot to provide office space for 1,000 workers" performance requirement - ANSWER describes what product(s) components must do/achieve with a measurement metric; challenges: developing objective and definable standards to validate performance, tendency to drift to prescriptive specs; examples: uniformat C10, interior construction. "Provide durable, paintable interior walls between the offices with STC 35 (min)"

Meer zien Lees minder
Instelling
DBIA
Vak
DBIA

Voorbeeld van de inhoud

DBIA EXAM 2025-2026 NEWEST
VERSION ACCURATE ACTUAL
EXAM COMPLETE QUESTIONS
AND CORRECT DETAILED
ANSWERS (VERIFIED ANSWERS)
|ALREADY GRADED A+ | WITH A
STUDY GUIDE

Project Delivery System - ANSWER How team members are organized,
establishes when parties engage, determines roles of parties, and
determines sequence of design, procurement, and construction (db, cmar,
dbb)

Procurement Method - ANSWER how team members are selected (QBS,
best value, low price, sole source)

contracting approach - ANSWER how team members are paid (fp, gmp,
cost reimbursement, target price, unit price)

Design-Bid-Build (DBB) - ANSWER linear, sequential process, A/E
selected on qualifications, GC selected on low price, design is fully
completed without input from GC, A/E acting in owner's interests, with a
historically strong bond, process is well-established and understood

construction manager at risk - ANSWER similar org structure to DBB,
construction manager selected by QBS or best value, contractor provides
precon services, negotiated gmp contracting approach, open book
estimating process, potential to fast track project, construction cost
determined before design completed, potential issues over what is
reasonably inferable from gmp design documents

Design-Build - ANSWER The owner contracts with one entity (a person
or firm) to provide both design and construction services, designer and
contractor have a direct contractual relationship, selected by QBS or best
value, wide spectrum of contracting approaches and organizational

,structures, single point responsibility, owner does not manage designer,
owner exposure to claims is significantly reduced

engineer procure construct (epc) - ANSWER similar to design build, in
industrial and power generation sectors, systems and performance testing
are central to scope, contractor will typically perform engineering with its
in-house staff, owner has need for single point responsibility, contracts
include plant and process performance guarantees, contract items include
performance and schedule liquidated damages and limitations of liability

Multiple Prime Contracting - ANSWER owner contracts with multiple
trade contractors, attributes are typically similar to dbb, owner's ability to
schedule and coordinate the work

Integrated Project Delivery (IPD) - ANSWER multi-party agreement -
all parties equal, QBS procurement and target pricing contract approach,
private sector use (limited at this time), key: owner's ability to accept risk

Lowest Price Technically Acceptable (LPTA) - ANSWER contract
requirements are clearly definable and minimal risk of unsuccessful
contract performance; suitable for commodities or simple service;
proposers do the minimum for the pass/fail process; impedes thinking
creatively or creating the best team; little practical ability for an owner to
ever fail someone

Sole source - ANSWER Only one vendor can provide what your project
needs to purchase. Examples include a specific consultant, specialized
service, or unique type of material. essentially non-competitive; multiple
contracting approaches available (unit rates, cost plus, GMP, or lump sum)

RFQ - ANSWER goal: to get highly qualified teams and information that
will serve to differentiate among proposers and evaluate past performance

RFP - ANSWER communicates needs for firm pricing; perform front-
end tasks (like geotech) for baselines; only asks for relevant and
reasonably needed information; allows ATCs when mandatory technical
criteria is established

public-private partnership (p3) - ANSWER Instead of government
building and maintaining major infrastructure (such as highway, water
treatment plant), build and maintenance is outsourced to a private
company. Opposed by public sector unions. this is not considered a

,delivery system but its underlying approaches are delivery systems and
typically use DB. multiple procurement and contracting approaches

shift left - ANSWER intense efforts to establish scope early in the
process; drives early team formation to include key trade subcontractors;
can enable big decisions to be made early, affect project outcomes at
lowest cost, establish a need for co-location and collaboration, and
compress time during concurrent design and construction

traditional design build - ANSWER typically two-phase best value
procurement with lump sum contract; owner defines project requirements
and scope of prescriptive work; use of performance-based technical
requirements with limited prescriptive specifications

progressive design build - ANSWER design and price are progressively
developed after the design-builder is under contract; final project cost and
schedule commitment is not established as part of the selection process;
two phases: preliminary services and final design and construction
services

criteria documents - ANSWER describe the end result

bridging documents - ANSWER prescribes how to achieve the end result

design bid build paradigm - ANSWER prior to bidding, owner
undertakes a process to design the project and all of its details to 100%
complete plans and specs. the owner is therefore responsible for success
or failure of details of the design, and warrants the sufficiency of design
to the contractor. the owner is therefore liable to the contractor for any
gaps between plans and specifications and owner's requirements for
project performance

design details responsibility - ANSWER the owner should define its
performance requirements and award the contract on the basis of
preliminary design; this makes the design-builder responsible for
completing the design in accordance with the owner's performance
requirements. that also causes the design-builder to warrant the
sufficiency of the design to meet the owner's criteria and the sufficiency
of the design to subcontractors/suppliers that have no design
responsibility

, uniformat - ANSWER subdivides project by functional elements, focuses
on systems and assemblies, useful for preliminary information and early
design phases, aligns with BIM models and conceptual estimating

masterformat - ANSWER subdivides work by results/trades, focuses on
building materials, products, and activities, useful for detailed
information during final design and construction phases, and aligns with
detailed estimating

functional requirement - ANSWER a specific business need or behavior
as seen by an external user of the system; describe what
functions/operations the end product must perform/accommodate;
examples: regulatory, permitting, economic, and others that define
functions and operational capability. "Build an office building on my
existing lot to provide office space for 1,000 workers"

performance requirement - ANSWER describes what product(s)
components must do/achieve with a measurement metric; challenges:
developing objective and definable standards to validate performance,
tendency to drift to prescriptive specs; examples: uniformat C10, interior
construction. "Provide durable, paintable interior walls between the
offices with STC 35 (min)"

prescriptive requirement - ANSWER describes in terms of exactly how
the product and/or its components must be built; cookbook approach;
developed by the design builder but used by owners in the RFP/bridging
documents for operability or maintenance needs and conditions of
permits or third parties; examples: uniformat C10, partitions. "Install
gypsum wallboard on 3-5/8" metal studs at 16" on center with XX
acoustical insulation per YY standards."

shortlisting - ANSWER takes the best of "qualified" teams; a key to
design-build success; not the same as prequalifying or pass/fail; keeping
this small increases interest among the best teams and minimizes
procurement costs for everyone including the owner

competitive procurement process - ANSWER owners define their goals
and selection criteria, one or 2 phase process if shortlisting is applicable,
price is not a factor in selection, award to most qualified proposer,
negotiate to a fair and reasonable price

QBS typical criteria - ANSWER qualifications, experience and past
performance of design build team, qualifications of key personnel,

Geschreven voor

Instelling
DBIA
Vak
DBIA

Documentinformatie

Geüpload op
5 augustus 2025
Aantal pagina's
44
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$14.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
DocPatricia Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
11
Lid sinds
1 jaar
Aantal volgers
0
Documenten
191
Laatst verkocht
1 week geleden
DOCPATRICIA STUDY HUB

**Need Help with Assignments, Test Banks, Essays, or Tutoring?** I offer high-quality academic assistance across a wide range of subjects and complexity levels. With a strong commitment to punctuality, I ensure all work is delivered on time and meets academic standards. Whether it’s research papers, case studies, psychology assignments, or other topics, I put my best effort into every project. Academic writing is a passion of mine—I take pride in crafting well-structured, engaging, and informative content tailored to your requirements. I’m dedicated to producing original work that follows proper formatting and exceeds expectations. **Refer a friend!** For every successful referral (completed and paid order), you’ll receive one free assignment as a thank-you. Let me take your assignments to the next level—send your instructions and I’ll handle the rest with fresh insights, clarity, and precision.

Lees meer Lees minder
3.8

4 beoordelingen

5
1
4
1
3
2
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen