1. What is the primary responsibility of a building project manager?
A. Design the building layout
B. Supervise on-site workers
C. Ensure the project is completed on time, within scope, and on budget
D. Approve architectural drawings
:Answer: C
Explanation: The project manager ensures timely, budget-conscious, and
scope-aligned project delivery.
2. What document outlines the specific goals, timeline, and resources for a
construction project?
A. Budget report
B. Project charter
C. Work order
D. Blueprint
:Answer: B
Explanation: The project charter defines the project objectives, scope,
stakeholders, and authority.
3. The Critical Path Method (CPM) is used to:
A. Determine job costs
B. Identify material suppliers
C. Establish project schedules
D. Allocate human resources
:Answer: C
Explanation: CPM identifies the longest sequence of tasks in a project that
must be completed on time.
,4. Which of the following is NOT a stage in the project management life cycle?
A. Initiation
B. Execution
C. Evaluation
D. Commissioning
:Answer: D
Explanation: Commissioning is a post-construction phase, not a core PM
lifecycle stage.
5. What is a Gantt chart used for?
A. Tracking costs
B. Managing safety audits
C. Scheduling project activities
D. Estimating labor needs
:Answer: C
Explanation: Gantt charts provide a visual timeline of project activities and
their durations.
6. What must be secured before any construction work begins in Florida?
A. Building permit
B. Certificate of occupancy
C. Fire code certificate
D. OSHA clearance
:Answer: A
Explanation: Building permits are required before legal commencement of
construction.
7. Who is responsible for enforcing building codes on site?
A. Architect
B. Project Manager
C. Building Inspector
D. General Contractor
:Answer: C
Explanation: Building inspectors ensure code compliance through site
inspections.
,8. Which type of insurance protects a project from damages during
construction?
A. Liability insurance
B. Workers’ compensation
C. Builders Risk Insurance
D. Equipment insurance
:Answer: C
Explanation: Builders Risk covers property damage during construction.
9. The term “float” in project scheduling refers to:
A. Budget margin
B. Unused materials
C. Extra time available for an activity without delaying the project
D. Contingency labor
:Answer: C
Explanation: Float is the amount of time a task can be delayed without
affecting the project timeline.
10. What is the purpose of a change order?
A. Approve payment
B. Modify the construction plan
C. Schedule a subcontractor
D. Close the project
:Answer: B
Explanation: Change orders authorize adjustments in project scope, time, or
cost.
11. What Florida code regulates building construction and permitting?
A. Florida Structural Act
B. Florida Building Code
C. Florida Residential Law
D. Florida Contractor’s Rulebook
:Answer: B
Explanation: The Florida Building Code governs all construction requirements
and permits.
, 12. What is the first step in developing a project schedule?
A. Estimating material cost
B. Identifying stakeholders
C. Defining project activities
D. Hiring subcontractors
:Answer: C
Explanation: Schedule planning begins by breaking the work into defined
activities.
13. A project stakeholder is:
A. Only the property owner
B. Anyone affected by or with interest in the project
C. Only subcontractors
D. Only the general contractor
:Answer: B
Explanation: Stakeholders include clients, users, contractors, regulators, etc.
14. Value engineering is best described as:
A. Cutting costs by using low-quality materials
B. Enhancing project value by optimizing function and reducing cost
C. Increasing contingency reserves
D. Eliminating labor-intensive tasks
:Answer: B
Explanation: Value engineering seeks to maintain function while reducing
costs.
15. What does a punch list include?
A. Budget overruns
B. Project milestones
C. Items to be completed or corrected before final acceptance
D. Daily attendance
:Answer: C
Explanation: A punch list outlines tasks needing completion before project
closeout.
A. Design the building layout
B. Supervise on-site workers
C. Ensure the project is completed on time, within scope, and on budget
D. Approve architectural drawings
:Answer: C
Explanation: The project manager ensures timely, budget-conscious, and
scope-aligned project delivery.
2. What document outlines the specific goals, timeline, and resources for a
construction project?
A. Budget report
B. Project charter
C. Work order
D. Blueprint
:Answer: B
Explanation: The project charter defines the project objectives, scope,
stakeholders, and authority.
3. The Critical Path Method (CPM) is used to:
A. Determine job costs
B. Identify material suppliers
C. Establish project schedules
D. Allocate human resources
:Answer: C
Explanation: CPM identifies the longest sequence of tasks in a project that
must be completed on time.
,4. Which of the following is NOT a stage in the project management life cycle?
A. Initiation
B. Execution
C. Evaluation
D. Commissioning
:Answer: D
Explanation: Commissioning is a post-construction phase, not a core PM
lifecycle stage.
5. What is a Gantt chart used for?
A. Tracking costs
B. Managing safety audits
C. Scheduling project activities
D. Estimating labor needs
:Answer: C
Explanation: Gantt charts provide a visual timeline of project activities and
their durations.
6. What must be secured before any construction work begins in Florida?
A. Building permit
B. Certificate of occupancy
C. Fire code certificate
D. OSHA clearance
:Answer: A
Explanation: Building permits are required before legal commencement of
construction.
7. Who is responsible for enforcing building codes on site?
A. Architect
B. Project Manager
C. Building Inspector
D. General Contractor
:Answer: C
Explanation: Building inspectors ensure code compliance through site
inspections.
,8. Which type of insurance protects a project from damages during
construction?
A. Liability insurance
B. Workers’ compensation
C. Builders Risk Insurance
D. Equipment insurance
:Answer: C
Explanation: Builders Risk covers property damage during construction.
9. The term “float” in project scheduling refers to:
A. Budget margin
B. Unused materials
C. Extra time available for an activity without delaying the project
D. Contingency labor
:Answer: C
Explanation: Float is the amount of time a task can be delayed without
affecting the project timeline.
10. What is the purpose of a change order?
A. Approve payment
B. Modify the construction plan
C. Schedule a subcontractor
D. Close the project
:Answer: B
Explanation: Change orders authorize adjustments in project scope, time, or
cost.
11. What Florida code regulates building construction and permitting?
A. Florida Structural Act
B. Florida Building Code
C. Florida Residential Law
D. Florida Contractor’s Rulebook
:Answer: B
Explanation: The Florida Building Code governs all construction requirements
and permits.
, 12. What is the first step in developing a project schedule?
A. Estimating material cost
B. Identifying stakeholders
C. Defining project activities
D. Hiring subcontractors
:Answer: C
Explanation: Schedule planning begins by breaking the work into defined
activities.
13. A project stakeholder is:
A. Only the property owner
B. Anyone affected by or with interest in the project
C. Only subcontractors
D. Only the general contractor
:Answer: B
Explanation: Stakeholders include clients, users, contractors, regulators, etc.
14. Value engineering is best described as:
A. Cutting costs by using low-quality materials
B. Enhancing project value by optimizing function and reducing cost
C. Increasing contingency reserves
D. Eliminating labor-intensive tasks
:Answer: B
Explanation: Value engineering seeks to maintain function while reducing
costs.
15. What does a punch list include?
A. Budget overruns
B. Project milestones
C. Items to be completed or corrected before final acceptance
D. Daily attendance
:Answer: C
Explanation: A punch list outlines tasks needing completion before project
closeout.