If your tilesetters had completed one wall and were about to start the other,
what should you have them do? - CORRECT-ANSWERSClick here to select
answer A.
reclean the first wall after 48 hours
Click here to select answer B.
wait 48 hours before starting the opposite (back) side of the same wall
Click here to select answer C.
double-grout the first side
Click here to select answer D.
repair the cracks
Answer:B
What is the maximum size a stone veneer slab may be before you must put
in metal rods? - CORRECT-ANSWERSClick here to select answer A.
560 sq in
,Click here to select answer B.
680 sq in
Click here to select answer C.
720 sq in
Click here to select answer D.
840 sq in
Answer:C
With which of the following should you clean the back of stone before
installation? - CORRECT-ANSWERSClick here to select answer A.
acetone
Click here to select answer B.
soap powder
Click here to select answer C.
acid
Click here to select answer D.
baking soda
,Answer:B
What is the correct joint size for tile 2-3/16" square or smaller? - CORRECT-
ANSWERSClick here to select answer A.
1/16" to 1/8"
Click here to select answer B.
1/8" to 1/4"
Click here to select answer C.
1/4" to 3/4"
Click here to select answer D.
1/8" to 1/2"
Answer:A
Which of the following should you not use for tile backing? - CORRECT-
ANSWERSClick here to select answer A.
flat-rib metal lath
, Click here to select answer B.
3/8" rib lath
Click here to select answer C.
diamond mesh
Click here to select answer D.
neither A nor B
Answer:D
What is the maximum height of a grab bar in a shower with disabled access?
- CORRECT-ANSWERSClick here to select answer A.
30"
Click here to select answer B.
33"
Click here to select answer C.
36"
Click here to select answer D.
QUESTIONS AND ANSWERS 2025
If your tilesetters had completed one wall and were about to start the other,
what should you have them do? - CORRECT-ANSWERSClick here to select
answer A.
reclean the first wall after 48 hours
Click here to select answer B.
wait 48 hours before starting the opposite (back) side of the same wall
Click here to select answer C.
double-grout the first side
Click here to select answer D.
repair the cracks
Answer:B
What is the maximum size a stone veneer slab may be before you must put
in metal rods? - CORRECT-ANSWERSClick here to select answer A.
560 sq in
,Click here to select answer B.
680 sq in
Click here to select answer C.
720 sq in
Click here to select answer D.
840 sq in
Answer:C
With which of the following should you clean the back of stone before
installation? - CORRECT-ANSWERSClick here to select answer A.
acetone
Click here to select answer B.
soap powder
Click here to select answer C.
acid
Click here to select answer D.
baking soda
,Answer:B
What is the correct joint size for tile 2-3/16" square or smaller? - CORRECT-
ANSWERSClick here to select answer A.
1/16" to 1/8"
Click here to select answer B.
1/8" to 1/4"
Click here to select answer C.
1/4" to 3/4"
Click here to select answer D.
1/8" to 1/2"
Answer:A
Which of the following should you not use for tile backing? - CORRECT-
ANSWERSClick here to select answer A.
flat-rib metal lath
, Click here to select answer B.
3/8" rib lath
Click here to select answer C.
diamond mesh
Click here to select answer D.
neither A nor B
Answer:D
What is the maximum height of a grab bar in a shower with disabled access?
- CORRECT-ANSWERSClick here to select answer A.
30"
Click here to select answer B.
33"
Click here to select answer C.
36"
Click here to select answer D.