OM 300 Exam 2 Chillcut Questions And Answers

Instelling
OM 300 Chillcut
Vak
OM 300 Chillcut

Voorbeeld van de inhoud

OM 300 Exam 2 Chillcut Questions And Answers

Question 1
Which of the following is NOT one of the three main phases of project management?
A) Planning
B) Scheduling
C) Auditing
D) Controlling
Correct Answer: C) Auditing
Rationale: The three primary phases of project management are Planning (defining the
project), Scheduling (allocating resources and time), and Controlling (monitoring and
correcting). Auditing is a separate function.

Question 2
During which phase of project management are goals set, the project defined, and the team
organized?
A) Planning
B) Scheduling
C) Controlling
D) Executing
Correct Answer: A) Planning
Rationale: The planning phase involves establishing the foundational elements of the
project, including its objectives, scope, work breakdown structure, and organizational
form.

Question 3
Relating people, money, and supplies to specific activities and relating those activities to each
other is the focus of which project management phase?
A) Planning
B) Scheduling
C) Controlling
D) Goal Setting
Correct Answer: B) Scheduling

,Rationale: The scheduling phase is where the timeline is created. It involves sequencing
activities, estimating durations, and allocating the necessary resources to each task.

Question 4
Which project management phase involves monitoring resources, costs, quality, and budgets, and
then revising plans as needed?
A) Planning
B) Scheduling
C) Controlling
D) Organizing
Correct Answer: C) Controlling
Rationale: The controlling phase is the ongoing process of tracking progress against the
plan, identifying variances, and taking corrective action to keep the project on track.

Question 5
A project organization structure is most helpful when:
A) The work is routine and repetitive.
B) The job is unique and somewhat unfamiliar to the existing organization.
C) The tasks are simple and independent.
D) The project has an indefinite timeline.
Correct Answer: B) The job is unique and somewhat unfamiliar to the existing organization.
Rationale: A project-based organization is ideal for unique, temporary endeavors that
require specialized skills and a focused effort that falls outside the normal day-to-day
operations of the company.

Question 6
Which of the following is a primary responsibility of a project manager?
A) Performing all the technical tasks of the project.
B) Ensuring the project comes in within budget and meets quality goals.
C) Securing the initial funding for the project.
D) Reporting directly to the company's shareholders.
Correct Answer: B) Ensuring the project comes in within budget and meets quality goals.

, Rationale: The project manager is ultimately responsible for the successful execution of the
project, which means meeting the triple constraints of time, cost, and quality.

Question 7
Which of the following is an example of an ethical issue a project manager might face?
A) Pressure to alter status reports to mask delays.
B) Being asked to create a detailed project schedule.
C) Receiving a risk mitigation plan from the team.
D) Communicating project goals to the team.
Correct Answer: A) Pressure to alter status reports to mask delays.
Rationale: Project managers can face ethical dilemmas such as being pressured to be
dishonest about project status, compromise quality, or accept inappropriate gifts.

Question 8
Which project scheduling technique is a network diagram that uses a single, deterministic time
estimate for each activity?
A) Gantt Chart
B) Critical Path Method (CPM)
C) Program Evaluation and Review Technique (PERT)
D) Factor-Rating Method
Correct Answer: B) Critical Path Method (CPM)
Rationale: CPM is a network-based technique that uses one specific time estimate for each
activity to determine the project's critical path and duration.

Question 9
What is the first step in both the PERT and CPM project management techniques?
A) Draw the network diagram.
B) Compute the critical path.
C) Define the project and prepare the work breakdown structure.
D) Assign time estimates to each activity.
Correct Answer: C) Define the project and prepare the work breakdown structure.
Rationale: Before any scheduling or analysis can occur, the project's scope must be clearly
defined and broken down into smaller, manageable work packages or activities.

Geschreven voor

Instelling
OM 300 Chillcut
Vak
OM 300 Chillcut

Documentinformatie

Geüpload op
10 augustus 2025
Bestand laatst geupdate op
29 oktober 2025
Aantal pagina's
34
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$21.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Beoordelingen van geverifieerde kopers

Alle 2 reviews worden weergegeven
8 maanden geleden

9 maanden geleden

5.0

2 beoordelingen

5
2
4
0
3
0
2
0
1
0
Betrouwbare reviews op Stuvia

Alle beoordelingen zijn geschreven door echte Stuvia-gebruikers na geverifieerde aankopen.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
DICKENS maryland university
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
2295
Lid sinds
1 jaar
Aantal volgers
6
Documenten
2110
Laatst verkocht
1 dag geleden
PROSTUDYHUB

4.9

987 beoordelingen

5
869
4
101
3
12
2
4
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen