1. True or False? A labor laws placard must be posted.: True
2. True or False? The GC shall ensure that all subcontractors and their
workers have secured, maintained, and complied with all required
licenses, permits and certificates relating to, or otherwise necessary or
appropriate for, the performance and completion of the work and all other
activities and obligations under the Contract Documents.: True
3. Which of the following is required to be present at the job site?
A. Safety Manual and up to date MSDS binder
B. SWPP certificate posted
C. Visitors sign in book
D. All of the Above: All of the above
4. The SWPP implementation sequence may be modified?: After consulting
with the project SWPP Designer (CEC) and, if required, the Project Owner and
receiving written approval.
5. True or False: the GC doesn't need to worry about access control after
possession.: False
6. When installing perimeter BMP controls:: Note locations and dates of
installation on the site map.
7. A SWPP Site Map will show all of the following except:
A. Locations of BMPs
B. Notices of Violation
C. Phasing and Sequence
D. Limits of Disturbance: B. Notices of Violation C
8. In what circumstances must your company run newly hired employees
through E-Verify?: Any new hire employees who will provide services to
Walmart in a mandatory E-Verify State: AL, AZ, GA, LA, MS, NC, SC, TN or UT.
9. Factors to consider when creating your schedule include:: Account for
the time it takes to install or implement BMP's between each phase of
construction 10. Which of the following is not a silt fence related deficiency?
A. Tears or holes in the fabric
B. Excessive sediment accumulation
C. Track out
D. Undercutting: C. Trackout
1/6
, SWPP Walmart Test
11. Requirements for managing stormwater activity on a construction site
are outlined in the following regulation:: NPDES
12. True or False: Subcontractors do not need a GC badge during the first
week of construction as this is the slowest time of the project.: False 13.
Runoff Controls include all but which of the following:
A. Rolled erosion control products
B. Diversions
C. Check dams
D. Slope drains: A. Rolled erosion control products
14. To reduce the possibility of undercutting in channels, you should:: Install
filter fabric under rock and similar materials placed within the stormwater
conveyance 15. In addition to Worker Verification and badging, what other
incidents and/or regulatory contacts may happen?: Immigration, E-Verify,
wages, harassment, discrimination and joint employment.
16. If a worker is removed during an audit, are they allowed back on site?:
Yes, if the auditor clears them.
17. When inspecting inlet protection look for all but one of the following:
A. Structural damage including torn fabric and broken supports
B. Restricted flow and bypass
C. Appropriate vegetative stabilization
D. Accumulated sediment and debris: C. Appropriate vegetative stabilization D
18. If you believe stormwater BMP modifications are necessary, you must::
Seek written approval from the project SWPP designer and, if required, the
project Owner.
19. Which of the following is NOT a beneficial use of water?
A. Swimming
B. Drinking
C. Flushing a spill down a storm drain
D. Industrial and agricultural water supply: C. Flushing a spill down a storm
drain
D
20. While inspecting filed BMPs, the SWPP inspector should perform all of
the following except:
A. Note BMPs in need of repair or maintenance