Construction quality management - Correct answerThe performance of tasks,
which ensure that construction is performed according to plans and specifications, on
time, within a defined budget, and a safe work environment.
Quality - Correct answerConformance to properly developed requirements
Purpose of CQM - Correct answerThe government's efforts, separate from, but
in coordination and cooperation with the contractor, assure that the quality set by the
plans and specifications is achieved.
Contractor quality control function - Correct answerTo assure that the completed
project meets all quality requirements of the contract.
Contractor benefits of CQM - Correct answerIncreased profit and production,
better communications, planning, improved organizational skills, and outstanding
performance evaluations to obtain future contracts.
Two factors cause construction industry to become highly specialized - Correct
answerChanging market and increased tech and regulations
Factors that will influence both the govt and construction industry in the future -
Correct answerNew govt regulations, greater influence from customer,
improvement of QC and QA requirements, construction-oriented mgmt info systems,
formal partnering involving stakeholders, more reliance on design-build, more
consideration for life cycle requirements, increased performance based incentives
Pre construction submittals - Correct answerRequired prior to or at start of
construction or the next major phase on a multi phase contract
Preconstruction submittals include: - Correct answerScheduled and a tabular list
of locations, features, and other pertinent information regarding products, materials,
equipment, or components to be used in work
, Product data - Correct answerCatalog cuts, illustrations, schedules, diagrams,
performance charts, instructions, systems and equipment
Samples - Correct answerFabricated or I fabricated physical examples of
materials, equipment, or workmanship that illustrate functional and aesthetic
characteristics of material or product that establish standards
Design data - Correct answerCalculations, mix designs, analyses pertaining to a
part of work
Test reports - Correct answerSigned by authorized official of laboratory that a
material, product or system to be provided has been tested in accord with specified
requirements, unless otherwise specified, must have been done within 3 years of date
of contract award
Certificates - Correct answerStatements printed on the manufacturer's letterhead
and signed by responsible officials of manufacturer's product, system, or material meets
spec requirements. Must be dated after award of project contract and clearly name the
project
Manufacturer's instructions - Correct answerPreprinted material describing
installation of a product, system, or material, including special notices and concerning
impedances, hazards, and safety instructions
Operation and maintenance data - Correct answerData provided by the
manufacturer, or system provider, including help and product line documentation,
necessary to maintain and install equipment for operating and maintenance use
Manufacturer's field reports - Correct answerDocumentation of the testing and
verification actions taken by manufacturer's representative at the job site, or on sample
taken from the job site, on a portion of the work, during or after installation to confirm
compliance with standards and instructions.
Must be signed by an authorized official of testing laboratory or agency and state the
test results to indicate pass or failure
Closeout Submittals - Correct answerDocumentation to record compliance with
technical or administrative requirements or to establish an administrative mechanism
Special requirements to end a contract or major phase if a multi phase contract
GPV - Correct answerGuiding principle validation