Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

LSU CM EXIT EXAM WITH ALL CORRECT & 100% VERIFIED ANSWERS|UPDATED TO PASS|ALREADY PASSED!!!

Beoordeling
-
Verkocht
-
Pagina's
7
Cijfer
A+
Geüpload op
16-08-2025
Geschreven in
2025/2026

LSU CM EXIT EXAM WITH ALL CORRECT & 100% VERIFIED ANSWERS|UPDATED TO PASS|ALREADY PASSED!!!

Instelling
Vak

Voorbeeld van de inhoud

LSU CM EXIT EXAM WITH ALL CORRECT & 100%
VERIFIED ANSWERS|UPDATED TO PASS|ALREADY
PASSED!!!

Conventional concrete typically weighs ____________ ✔Correct answer-140pcf - 150pcf

BTU ✔Correct answer-British Thermal Unit - A quantity of heat. It is the amount of heat needed to
raise a pound of water 1°F. An MBH is 1,000 BTUs/hr.

Sensible Heat ✔Correct answer-"Dry Heat" - Heat added to the air without adding moisture. As
sensible heat increases the points on the psychrometric chart move to the right.

Latent Heat ✔Correct answer-The hidden heat added to the air by adding moisture (approx. 1,000
BTUs/lb of water). As latent heat increases the points on the psychrometric chart move up.

Enthalpy ✔Correct answer-(h) - is the total amount of thermal energy (sensible & latent) in the air.
It is measured in BTUs per lb of dry air.

Depreciable value is the purchase price less the __________ ✔Correct answer-Salvage Value

The difference between a current asset and a long term asset is ______________ ✔Correct
answer-Current assets can be liquidated within one year and long term assets cannot

Current Ratio ✔Correct answer-This accounting ratio is calculated by dividing the total current
assets by the total current liabilities

Working capital of a construction company increases when ✔Correct answer-A company sells
equipment or assets

When an owner decides to add additional work to the original scope, this is considered what type of
change? ✔Correct answer-Owner Directed Change Order

All of the following are steps that a construction company can follow in applying risk management
except one. ✔Correct answer-Avoid all risky situations.

Complete the risk statement...if a/an _______________ happens, then the steel material for the
project may cost more than the budget, which will impact the stele subcontractors, causing an
increase in the project cost. ✔Correct answer-Fluctuation in the steel price.

Which of the following best describes risk? ✔Correct answer-The potential event that results in an
outcome that is different than what's planned.

Typical steps associated with the risk management process are identify the risk, analyze the
identified risks, _____________, allocate risks contractually, and monitor and control risks
throughout the design and construction of a project. ✔Correct answer-Mitigate and plan to
address risks.

, Which of the following is not a risk identification tool and technique that construction managers use.
✔Correct answer-Value Engineering

Change Order ✔Correct answer-A written order to the contractor authorizing changes in work to
the signed original documents (not the bid documents)

An acceptance is ______________________________. ✔Correct answer-An unconditional
agreement with an offer

What is the constructive acceleration? ✔Correct answer-It is the forced completion of the contract
work in a shorter period than should have been allowed by the issuance of a warranted time
extension.

What is the cardinal rule of documentation and records? ✔Correct answer-Put it in writing.

Which one of the following is NOT an alternative dispute resolution method? ✔Correct answer-
Litigation

__________________ is a sum withheld from progress payments to the contractor in accordance
with the terms of
the contract ✔Correct answer-Retainage (retention)

Define progress curves. ✔Correct answer-A display of cumulative costs, labor hours, or other
quantities against time as s-curves.

From the following list, which tool does not help a project manager to control costs on a project?
✔Correct answer-Baseline schedules

If a project that is 40% complete has a cost variance of -$45,000, what does this mean? ✔Correct
answer-The project is currently $45,000 over-budget

In earned value, if a project has a BCWP equal to $5,000, what does the $5,000 represent?
✔Correct answer-The Earned Value of the Project

Which one of the following would a project manager not find the information needed to calculate
and plot the ACWP for an earned value analysis? ✔Correct answer-Three-week look ahead
schedule

Define earned value: ✔Correct answer-A project management methodology used to track project
performance and forecast future performance.

Your project budgets and schedules were updated. Using the chart below, which best describes the
status of the ✔Correct answer-Under budget relative to the amount of work accomplished.

Your project budgets and schedules were updated. Using the chart below, which best describes the
status of the project: ✔Correct answer-Ahead of schedule

A lower standard deviation indicates: ✔Correct answer-Less dispersion of the data.

_____________is used to statistically analyze if two quality control samples have a difference in
means. ✔Correct answer-t-test

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
16 augustus 2025
Aantal pagina's
7
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Studyclub Yale School Of Medicine
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
50
Lid sinds
1 jaar
Aantal volgers
1
Documenten
11132
Laatst verkocht
10 uur geleden
"The Club for Top Academic Performance."

Welcome to StudyClub—the ultimate destination for students who want to make studying not only effective but also enjoyable! Whether you’re preparing for an exam, looking to improve your grades, or mastering new subjects, StudyClub is your go-to space to find the tools and resources you need to succeed. At StudyClub, I believe in the power of community. That’s why I’ve created a collection of high-quality study materials designed to simplify complex concepts and help you achieve your academic goals. Whether you’re an individual looking to study independently or a student seeking the support of a virtual study group, you’ll find everything you need to succeed. Join the StudyClub today, where learning is made easier, more organized, and—most importantly—more collaborative. Let’s grow together, learn smarter, and unlock your academic potential. Thank you for being part of the StudyClub community. I can’t wait to see you succeed!

Lees meer Lees minder
3.6

13 beoordelingen

5
6
4
1
3
3
2
1
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen