1. According to CCR, Title 23 UST Regulations, What is the frequency that the
Monitor Certification must be performed?: Every 12 Months
2. If visual monitoring is utilized as the means of release detection for single
walled tank, it must be conducted on a Basis.: Daily
3. The Purpose of spill and overfill protection equipment is to minimize the
potential for a release during:: Fuel Deliveries
4. Which of the following is a potential symptom of toxic petroleum exposure:-
: Dizziness
Tremors
Eye irritation
mailto:https://www.stuvia.com/en-us/user/techgrades
,mailto:https://www.stuvia.com/en-us/user/techgrades
All of the above(correct)
5. Under-Dispenser Containment is required for underground storage
tank systems: All
6. All of the following are true for Automatic Tank Gauging (ATG) except
for:: ATG system are required to be installed in all UST system
7. According to CCR Title 23, UST regulations Spill containment (spill bucket)
must meet all of the following requirements except:: Be installed on vent risers
8. Suction piping may not require leak detection if it has one check valve
located where?: Directly below the suction pump
9. Service Technician performing work on Monitoring equipment must be
trained and certified by : The manufacture of the equipment.
10. Air monitoring must be conducted when performing work within
a confined space.: Prior to and during
11. A UST Service Technician must be recertified by the equipment Manufac-
ture at the time interval recommended by the equipment manufacture or at
least every months, whichever is greater.: 36 Months
12. When an automatic tank gauge is utilized for single-walled tank leak detec-
tion, it shall test the tank at least monthly after product delivery or when the
tank is filled to within percent of the highest operating level during the
previous month.: 10
13. The following is true of spill buckets except:: Must provide drainage for
spilled product into the secondary containment sump.
14. If during an inspection of dispensing equipment at a retail gas station you
mailto:https://www.stuvia.com/en-us/user/techgrades
,mailto:https://www.stuvia.com/en-us/user/techgrades
find that the product is dispensing at a significant lower rate than usual. You
should check:: For piping leaks.
15. According to CCR title 23, UST Regulations the local agency must be
notified by the Owner/Operator how long before conducting Secondary Con-
tainment Testing?: At least 48 hours before the test.