Stakeholder analysis is an essential technique in the Identify Stakeholders process. One of the steps
involved is to classify the stakeholders based on their level of authority and their concern for the
project. Which of the following is a valid model used for this purpose?
A. Salience Model
B. Influence/Impact Grid
C. Power/Interest Grid
D. Power/Influence - correct answersC. Power/Interest Grid
Which of the following is a tool or technique used in the Manage Quality process?
A. Meetings
B. Expert Judgement
C. Process Analysis
D. Additional Quality Planning Tools - correct answersC. Process Analysis
You are a project manager. Your project is on a tight schedule. Several quality defects have been
discovered, causing the Customer concern. You would like to begin by tracking the causes that have the
highest number of associated defects. Which tool shows the defects by volume from greatest to least?
A. Cause-and-Effect diagram
B. Fishbone Diagram
C. Pareto Chart
D. Scatter Diagram - correct answersC. Pareto Chart
The CPI= 1.01 and the SPI=0.93. How is your project doing?
A. Behind schedule and over budget
B. Ahead of schedule and under budget
C. Ahead of schedule and over budget
D. Behind schedule and under budget - correct answersD. Behind schedule and under budget