Term
The issuance of a certificate for payment will constitute a
representation by the architect to the owner, that to the best of the
architect's knowledge that the architect has:
Give this one a try later!
verified that the project is on approved all change orders and
schedule modifications
, observed that the quality of
the work is in accordance confirmed that all materials
with the contract are sourced correctly
documents
Don't know?
2 of 84
Term
According to A201, after the Initial Decision Maker renders a
decision approving or rejecting a claim, either party may,
within___________________________________________________from
the date of an initial decision, demand in writing that the other party
file for mediation.
Give this one a try later!
60 days 45 days
15 days 30 days
Don't know?
3 of 84
Term
A construction change directive signed by the contractor shall be
effective immediately and shall be recorded as:
,Give this one a try later!
a final punch list a change order
a special inspection a calendar day
Don't know?
4 of 84
Term
According to A201, the issuing of certificates for payments will be
the duty of the:
Give this one a try later!
civil engineer general contractor
owner and contractor architect
Don't know?
, 5 of 84
Term
According to AIA documents, unless otherwise provided, Contract
Time is the Period of time:
Give this one a try later!
allotted in the Contract
Documents for Substantial
Completion of the Work, reserved for preliminary site work,
including authorized without extensions
adjustments.
allotted for project planning and designated for final inspections and
design, excluding adjustments approvals only
Don't know?
6 of 84
Term
If a change in work is requested by the architect and the owner,
but not agreed to by the contractor, than in absence of total
agreement by all parties, the architect can prepare a __________ and
make the
contractor promptly proceed with the change in the work involved.
Give this one a try later!