USATCES has submitted your ESSP for final approval. Who did they submit to? - -answer--
DDESB
What is the minimum distance permitted between an A&E location and the installation
headquarters building? - -answer--Inhabited Building Distance (IBD)
What is the minimum distance permitted between a PES and an interstate highway? - -
answer--Public Traffic Route Distance (PTRD)
What is the minimum distance permitted between any two operating buildings and sites
within an operating line? - -answer--Intraline Distance (ILD)
What is the minimum distance permitted between an earth-covered magazine and a nearby
above-ground magazine? - -answer--Intermagazine Distance (IMD)
What do you call the collection of documents that identifies the relationship between a PES
and any facilities or personnel who may be exposed to the PES? - -answer--ESSP
Your installation is putting a new roof on an existing PES facility. Do you need to complete an
ESSP? - -answer--No, this type of change does not require one
Your installation is changing the NEW of an existing facility and will be storing a hazard
division not previously approved in it. Do you need to complete an ESSP? - -answer--Yes, and
it must be approved by the DDESB
, 2
Which of the following is a phase of the ESSP process? - -answer--Development and
Evaluation
How many ESSP categories are there? - -answer--Five
how must the ESSP package be submitted? - -answer--Electronically
Which three items are in the Maps and Drawings section of an ESSP package? - -answer--
Facilities maps
Installation maps
Site maps
Which three items are included in the Evaluations section of an ESSP package? - -answer--
Electrical installation
Lightning protection information
Glass hazard risk assessment
What part of the ESSP package contains background information, site location, and reason for
the ESSP? - -answer--ESSP narrative
Who has ultimate approval authority for an ESSP? - -answer--DoD explosives Safety Board
(DDESB)
The purpose of an Expedited Approval Request is to - -answer--Justify why an expedited
approval is required
ARMY EXPLOSIVES SAFETY SITE PLANNING (CERT)/ EXPLOSIVE
SAFETY SITE PLANNING PROCESS (AMMO-100) LATEST UPDATE
2025 BEST EXAM GUIDE QUESTIONS AND ANSWERS
USATCES has submitted your ESSP for final approval. Who did they submit to? - -answer--
DDESB
What is the minimum distance permitted between an A&E location and the installation
headquarters building? - -answer--Inhabited Building Distance (IBD)
What is the minimum distance permitted between a PES and an interstate highway? - -
answer--Public Traffic Route Distance (PTRD)
What is the minimum distance permitted between any two operating buildings and sites
within an operating line? - -answer--Intraline Distance (ILD)
What is the minimum distance permitted between an earth-covered magazine and a nearby
above-ground magazine? - -answer--Intermagazine Distance (IMD)
What do you call the collection of documents that identifies the relationship between a PES
and any facilities or personnel who may be exposed to the PES? - -answer--ESSP
Your installation is putting a new roof on an existing PES facility. Do you need to complete an
ESSP? - -answer--No, this type of change does not require one
Your installation is changing the NEW of an existing facility and will be storing a hazard
division not previously approved in it. Do you need to complete an ESSP? - -answer--Yes, and
it must be approved by the DDESB
, 2
Which of the following is a phase of the ESSP process? - -answer--Development and
Evaluation
How many ESSP categories are there? - -answer--Five
how must the ESSP package be submitted? - -answer--Electronically
Which three items are in the Maps and Drawings section of an ESSP package? - -answer--
Facilities maps
Installation maps
Site maps
Which three items are included in the Evaluations section of an ESSP package? - -answer--
Electrical installation
Lightning protection information
Glass hazard risk assessment
What part of the ESSP package contains background information, site location, and reason for
the ESSP? - -answer--ESSP narrative
Who has ultimate approval authority for an ESSP? - -answer--DoD explosives Safety Board
(DDESB)
The purpose of an Expedited Approval Request is to - -answer--Justify why an expedited
approval is required