Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CIT 492 FINAL ACTUAL EXAM NEWEST 2025/2026 WITH COMPLETE QUESTIONS AND CORRECT ANSWERS |ALREADY GRADED A+||BRAND NEW VERSION!

Beoordeling
-
Verkocht
-
Pagina's
25
Cijfer
A+
Geüpload op
31-08-2025
Geschreven in
2025/2026

CIT 492 FINAL ACTUAL EXAM NEWEST 2025/2026 WITH COMPLETE QUESTIONS AND CORRECT ANSWERS |ALREADY GRADED A+||BRAND NEW VERSION! Hammock activities allow: - ANSWER-The project team to better disaggregate the overall project network into logical summaries. An activity has an optimistic time estimate of 17 days, a most likely estimate of 22 days, and a pessimistic estimate of 32 days. What is the expected duration of the activity? - ANSWER-22.83 Days Which technique would accelerate the completion of a project? - ANSWER Laddering Summaries for some subsets of the activities identified in the overall project network are called: - ANSWER-Hammock Activities These can be located by doing a backward pass through a network. - ANSWER Burst Activities Concurrent activities are: - ANSWER-Activities that can be performed at the same time What is the slack time for Activity D given the activity times and precedence requirements shown in the table? ActivityTimePredecessorA5--B7--C8AD7AE4BF8C, DG9E, FH7G - ANSWER-1 2 | Page CIT 492 Final Actual EXAM An activity has an optimistic time estimate of 12 days, a most likely estimate of 16 days, and a pessimistic estimate of 22 days. What is the expected standard deviation of the activity? - ANSWER-Between 1 and 2 days A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 33 weeks? ActivityNormal timeCrash timeNormal CostCrash CostPredecessorA85$1,0002,000 B641,5002,000AC851,8002,300AD1291,0001,800BE,450BF971,5001,90 0C, DG752,3002,800E, F - ANSWER-$12,250

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

CIT 492 Final Actual EXAM


CIT 492 FINAL ACTUAL EXAM NEWEST 2025/2026 WITH
COMPLETE QUESTIONS AND CORRECT ANSWERS |ALREADY
GRADED A+||BRAND NEW VERSION!
Hammock activities allow: - ANSWER-The project team to better disaggregate the
overall project network into logical summaries.


An activity has an optimistic time estimate of 17 days, a most likely estimate of 22
days, and a pessimistic estimate of 32 days. What is the expected duration of the
activity? - ANSWER-22.83 Days


Which technique would accelerate the completion of a project? - ANSWER-
Laddering


Summaries for some subsets of the activities identified in the overall project
network are called: - ANSWER-Hammock Activities


These can be located by doing a backward pass through a network. - ANSWER-
Burst Activities


Concurrent activities are: - ANSWER-Activities that can be performed at the same
time


What is the slack time for Activity D given the activity times and precedence
requirements shown in the table?
ActivityTimePredecessorA5--B7--C8AD7AE4BF8C, DG9E, FH7G - ANSWER-1

1|Page

, CIT 492 Final Actual EXAM



An activity has an optimistic time estimate of 12 days, a most likely estimate of 16
days, and a pessimistic estimate of 22 days. What is the expected standard
deviation of the activity? - ANSWER-Between 1 and 2 days


A project has the activity duration and cost information indicated in the table
where all times are in weeks. What is the lowest total cost for completing this
project in 33 weeks?
ActivityNormal timeCrash timeNormal CostCrash CostPredecessorA85$1,0002,000
B641,5002,000AC851,8002,300AD1291,0001,800BE14119501,450BF971,5001,90
0C, DG752,3002,800E, F - ANSWER-$12,250


AOA networks have an advantage over AON networks: - ANSWER-If the project is
complex.


A gentleman farmer maniacally works on academic projects to raise funds for his
true passion, farming. He has identified seven tasks and developed three time
estimates (all in days) of the next big project on the farm, replacing the fence at
the comedy pasture. Tasks, precedence requirements, and time estimates are
shown in the table. What is the late finish for the Plant Posts activity?
ActivityOptimistic timeMost Likely timePessimistic timePredecessorCorner
Posts456--String Line789--Dig Holes101214Corner PostsPlant Posts111417String
LineWeld Top Bar81114String LinePaint91113Dig Holes, Plant PostsTack
Wire91216Weld Top Bar - ANSWER-22 Days`


A gentleman farmer maniacally works on academic projects to raise funds for his
true passion, farming. He has identified seven tasks and developed three time
estimates (all in days) of the next big project on the farm, replacing the fence at
2|Page

, CIT 492 Final Actual EXAM

the comedy pasture. Tasks, precedence requirements, and time estimates are
shown in the table. What is the probability that the project is completed in 31
days?
ActivityOptimistic timeMost Likely timePessimistic timePredecessorCorner
Posts456--String Line789--Dig Holes101214Corner PostsPlant Posts111417String
LineWeld Top Bar81114String LinePaint91113Dig Holes, Plant PostsTack
Wire91216Weld Top Bar - ANSWER-0.055


An activity has an expected duration and an expected cost. Another name for an
activity is a(n): - ANSWER-Work Package


Use the Gantt chart and the activity list to determine which resource is needed
earliest in this project.
ActivityResourcesActivityResourcesA5F2B6G3C7H4D1J5E2K1 - ANSWER-Resource
2


Use the information in the table (all times are in days) to determine the lowest
extra cost for an 18-day project if the base cost for each activity finished in normal
time is $1,000.
ActivityNormal TimeMinimum TimeCrash Cost ($/day)PredecessorA106$70--
B63$40--C22--BD42$60CE64$80AF85$90D, E - ANSWER-$460


An activity has an optimistic time estimate of 17 days, a most likely estimate of 23
days, and a pessimistic estimate of 37 days. What is the variance of the activity? -
ANSWER-11.11




3|Page

Geschreven voor

Vak

Documentinformatie

Geüpload op
31 augustus 2025
Aantal pagina's
25
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$13.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
SophiaBennettRN Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
24
Lid sinds
1 jaar
Aantal volgers
1
Documenten
2262
Laatst verkocht
1 week geleden
TopGrade Tutor: Expert Psychology, Nursing, Pharmacology & Computer and Math Resources

Welcome to my academic support store, your trusted destination for top-tier homework help and tutoring services! Specializing in key subjects like Psychology, Nursing, Human Resource Management, and Mathematics, I’m dedicated to helping students excel with high-quality, meticulously crafted resources. My mission is to deliver scholarly, reliable content that guarantees excellent grades, earning me a reputation as one of Stuvia’s BEST GOLD RATED TUTORS. Whether you need assistance with quizzes, exams, or detailed study materials, I prioritize your success with a commitment to academic excellence and results you can count on

Lees meer Lees minder
3.9

7 beoordelingen

5
4
4
1
3
0
2
1
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen