Hammock activities allow: - ANSWER-The project team to better disaggregate the
overall project network into logical summaries.
An activity has an optimistic time estimate of 17 days, a most likely estimate of 22
days, and a pessimistic estimate of 32 days. What is the expected duration of the
activity? - ANSWER-22.83 Days
Which technique would accelerate the completion of a project? - ANSWER-
Laddering
Summaries for some subsets of the activities identified in the overall project
network are called: - ANSWER-Hammock Activities
These can be located by doing a backward pass through a network. - ANSWER-
Burst Activities
Concurrent activities are: - ANSWER-Activities that can be performed at the same
time
What is the slack time for Activity D given the activity times and precedence
requirements shown in the table?
ActivityTimePredecessorA5--B7--C8AD7AE4BF8C, DG9E, FH7G - ANSWER-1
1|Page
, CIT 492 Final Actual EXAM
An activity has an optimistic time estimate of 12 days, a most likely estimate of 16
days, and a pessimistic estimate of 22 days. What is the expected standard
deviation of the activity? - ANSWER-Between 1 and 2 days
A project has the activity duration and cost information indicated in the table
where all times are in weeks. What is the lowest total cost for completing this
project in 33 weeks?
ActivityNormal timeCrash timeNormal CostCrash CostPredecessorA85$1,0002,000
B641,5002,000AC851,8002,300AD1291,0001,800BE14119501,450BF971,5001,90
0C, DG752,3002,800E, F - ANSWER-$12,250
AOA networks have an advantage over AON networks: - ANSWER-If the project is
complex.
A gentleman farmer maniacally works on academic projects to raise funds for his
true passion, farming. He has identified seven tasks and developed three time
estimates (all in days) of the next big project on the farm, replacing the fence at
the comedy pasture. Tasks, precedence requirements, and time estimates are
shown in the table. What is the late finish for the Plant Posts activity?
ActivityOptimistic timeMost Likely timePessimistic timePredecessorCorner
Posts456--String Line789--Dig Holes101214Corner PostsPlant Posts111417String
LineWeld Top Bar81114String LinePaint91113Dig Holes, Plant PostsTack
Wire91216Weld Top Bar - ANSWER-22 Days`
A gentleman farmer maniacally works on academic projects to raise funds for his
true passion, farming. He has identified seven tasks and developed three time
estimates (all in days) of the next big project on the farm, replacing the fence at
2|Page
, CIT 492 Final Actual EXAM
the comedy pasture. Tasks, precedence requirements, and time estimates are
shown in the table. What is the probability that the project is completed in 31
days?
ActivityOptimistic timeMost Likely timePessimistic timePredecessorCorner
Posts456--String Line789--Dig Holes101214Corner PostsPlant Posts111417String
LineWeld Top Bar81114String LinePaint91113Dig Holes, Plant PostsTack
Wire91216Weld Top Bar - ANSWER-0.055
An activity has an expected duration and an expected cost. Another name for an
activity is a(n): - ANSWER-Work Package
Use the Gantt chart and the activity list to determine which resource is needed
earliest in this project.
ActivityResourcesActivityResourcesA5F2B6G3C7H4D1J5E2K1 - ANSWER-Resource
2
Use the information in the table (all times are in days) to determine the lowest
extra cost for an 18-day project if the base cost for each activity finished in normal
time is $1,000.
ActivityNormal TimeMinimum TimeCrash Cost ($/day)PredecessorA106$70--
B63$40--C22--BD42$60CE64$80AF85$90D, E - ANSWER-$460
An activity has an optimistic time estimate of 17 days, a most likely estimate of 23
days, and a pessimistic estimate of 37 days. What is the variance of the activity? -
ANSWER-11.11