Your quiz has been submitted successfully.
n1 point
During which phase of the SDLC is the database specification developed?
A) study phase
B) design phase
C) development phase
D) operational phase
View Feedback
n2 point
Which of the SDLC models has distinct goals for each phase of the development and requires each
phase to be fully completed before the next phase can begin?
A) fountain model
B) waterfall model
C) build and fix model
D) Rapid prototyping model
View Feedback
n3 point
During which phase of the SDLC are the software and hardware specifications developed?
A) study phase
B) design phase
C) development phase
D) operational phase
View Feedback
n4 point
Which of the following are risks associated with outsourcing? (select all that apply)
, A) difficulty in managing costs
B) increased liability
C) difficuty in bringing the business process back inhouse
D) movement of assets off the books
View Feedback
n5 point
True or false: The number of life cycle phases can vary from system to system and according to the
needs of the organization.
True
False
View Feedback
n6 point
During which phase of the SDLC is the user need identified?
A) study phase
B) design phase
C) development phase
D) operational phase
View Feedback
n7 point
Which of the following conditions would point to an organization building its own system versus buying
one? (select all that apply)
A) the process to be supported by the system is a strategic process for the organization
B) the available systems have many more features than the organization requires
C) the organization has a well-staffed and well-managed internal application development staff
D) the organization wants to maintain flexibility in phasing the implementation
View Feedback
n8 point
During which phase of the 4-Phase SDLC is user acceptance testing performed?