Combined Service Mains - ANS -This standard shall apply to ______ intended to
carry water for fire service mains
AHJ - ANS -Working plans shall be submitted for approval to the _____ before any
equipment is installed or remodeled.
Pressure-Regulating devices - ANS -____ shall not be used
Control Valves - ANS -______ shall not be installed in the piping from the fire
department connection to the fire service main
Control Valves - ANS -_____ shall be permitted in the system downstream of the
fire department connection
Check Valve - ANS -When more than one water supply exists, a ___________ shall
be installed in each connection
Control Valve - ANS -All check valves shall have a ________ installed upstream
and downstream of the check valve.
40 ft - ANS -A post indicator valve installed not less than____ from the building
32-40 inches - ANS -Where post indicator valves are used, they shall be set so that
the top of each post is _______ above final grade
not be required - ANS -Supervision of underground gate valves with roadway
boxes shall ____________
not be less than 6 inches - ANS -The connection from the hydrant to the main
shall ___________