(1) Central PMO - correct answer- - Supports several corporate
projects
- Supports people, performance, systems & processes
Benefits: flexible and effective in supporting a large number of small
projects.
(1) Embedded PMO - correct answer- - dedicated to single project
- for larger projects requiring lots of support
- Integral part of project team, providing range of services
- Supports people, performance & systems, with processes being
managed at programme/portfolio level
Benefits: high level of dedicated support to project, close
communications, releases PM to manage the project.
(1) Functional Organisation Structure - correct answer- - Functional
teams
- Primarily BAU/Deparmental Projects
- Common for orgs providing std products (e.g. manuf.)
(1) Functional Organisation Structure Advantages - correct answer- -
Staff gain technical expertise
,- Good functional problem solving
- Peer learning straight forward
- Job Security
- Clear career progression
(1) Functional Organisation Structure Disadvantages - correct answer-
- Corporate projects become difficult due to "Siloed" nature
- Functions prioritise their own functions work over others - inward
looking
- Remote from customer
(1) Governanace Layers - correct answer- 1. corporate (vision,
mission, strategy);
2. BAU (operations);
3. Business Change (projects, programmes).
(1) Governanance Benefits - correct answer- 1. Link to strategic
direction: for projects/programmes/portfolios
2. Clear ownership & leadership, using RACI.
3. Effective stakeholder engagement, through clear accountability, use of
stakeholder analysis.
4. Project & risk management through use of policies & procedures.
5. Consideration of long term value through linking to strategy.
,6. Can be audited, giving management team assurance, and ability to
correct & improve.
7. standardises methods of working
8. clarifies roles and increases efficiency
9. ensures conformance to standards and policies, facilitates full
disclosure and reporting.
(1) Governance - correct answer- - framework of authority &
accountability
- defines & controls outputs, outcomes & benefits.
(1) Governance Concepts - correct answer- 1. Portfolio direction and
alignment
2. Programme and Project sponsorship
3. Change and Project Management Capability
4. Transparency and Assurance
5. Culture and Ethics (inc. professional standards & behaviours)
(1) Governance Principles - correct answer- 1. Board responsible for
governance of project management (GoPM)
2. Roles and responsibilities clearly defined
3. Application throughout the lifecycle
4. Relationship between business strategy and portfolio
, 5. Clear plans with decision points
6. Effective delegation of decision making
7. Business case validity
8. Independent scrutiny planned and implemented
9. Clearly defined reporting and escalation
10. Open and honest reviews and culture of improvement
11.Appropriate engagement of stakeholders
12. Use of delegated responsibilities: clarifies roles and increases
efficiency
13. Use of processes and procedures: standardises methods of working
14. Use of regulations: ensures conformance to standards and policies,
facilitates full disclosure and reporting.
(1) Hub and Spoke PMO - correct answer- - In large organisations, the
central/hub PMO supports corporate portfolio, with spoke PMO's
supporting different departments' projects
- Supports people & performance, with processes & systems managed at
programme/portfolio level
Benefits: effective for managing information and processes.
(1) Matrix Organisation Structure - correct answer- - Still may have
functional teams - but temporary functional teams created for projects
- Draw staff from permanent functional postings
- Typical for orgs that have frequent change initiatives + BAU